Progress Report > Package IV - Mechanical Works
Photographs Summary Water Supply and Treatment System: Reinforcing steel bars for High Level Reservoir installed. Continue the Hydrant piping installation in the main tunnel. Start Piping installation and construction of Intake reservoir in South Portal Plaza. Tunnel Ventilation System: Continue construction of Epstations
Ventilation Adit Building: Concrete placed for columns, beams, roof slabs, chimney and wall. Construction Supervision 1) Water Supply and Treatment System + Installation of water pipes in the main tunnel
2) South Portal Plaza Excavation and Bedding 183 m3 Piping Work 120 m Backfill 270 m3 3) Tunnel Ventilation System + EP1 - EP base installed - EP Fan pedestal assembled - Form work and steel bar arrangement of strip footing for EP room started - ALC boards being installed for ceiling - EP Fan Duct installed + EP2 - Framework for ceiling installed - Brackets for EP, EP Fan and crane installed + EP3 - EP base installed - EP Fan pedestal assembled - Form work and steel bar arrangement of strip footing for EP room started - ALC boards being installed for ceiling - Measuring and anchoring for Duct and nozzle + Jet Fan - Assembly of 23 sets of Jet Fans completed 4) Ventilation Adit Building + Continuing concrete placing for columns, roof slabs, chimney and wall 5) Ventilation Adit Connection Measuring, marking and anchoring for Duct and nozzlePrevious
month
/ Next month
This homepage is presented by the Consultant Team Any further question should be forwarded to Webmaster or Consultant Team
|
|
||||||||||||||