Welcome to Our Site!
 

 

Public Relations > Knowledge Management

This page is a start point of our Knowledge Management (KM) for the Project. We are intending to establish our system for 1) Techinical Knowlegde, 2) Administrative Knowlegde, 3) Project Management Knowledge, and so on. If you have any further useful question and information, please email us. Thank you.

 

TECHNICAL KNOWLEGDE

1. Introduction of NATM

2. What is NATM?

3. Basic theory of soft ground tunnelling

1. What is "top heading" and "benching" in tunnel excavation?

2. What is a "round"?

 

NATM (New Autrian Tunneling Method)

1 . Introduction of NATM 

New Austrian Tunneling Method (NATM) is applied to the Project for its design and construction method of the tunnel. The NATM was developed by Austrian engineers such as RABCEWICZ from 1957 to 1965. The principles of the method is that observations should be undertaken to confirm that the support is adequately stabilizing the surrounding ground, so that the rate of convergence towards the tunnel is perceived to be approaching an asymptotic value. Where, after initial support, this is not assured, further support may be applied incrementally. Thus, the principle of the system may be described as that of ‘incremental support’. The essence of design of a system of incremental support is to understand the stress-strain properties of the ground and of the tunnel support since, essentially, controlled strain of the ground has to occur in order to develop a changed stress field in the ground around the tunnel compatible with the degree of support. The NATM has now gained general acceptance in the engineering world through the years of construction practices in various field such as highway, railway, and waterway.

2. What is NATM?

NATM represents for New Austrian Tunnelling Method. The NATM may be defined as a method of producing underground space using all available means to develop the maximum self-supporting capacity of the rock or soil to provide the stability of the underground opening. This is achieved by the application of a smooth and appropriately resistant initial support and a final lining which should accept the necessary deformation but guard against the development of rock load. The initial lining may consist of shotcrete, steel arches, and rockbolts, either singly or in combination. 

Simplified definition of the principles and effects of the NATM

3. Basic theory of soft ground tunnelling

Soft ground can be compared to a highly viscose liquid with a limited stand up time when excavated. This fact leads to the most important requirements of the NATM:

  • The excavated cross section should always be an ovoid shape.
  • Immediate, continuous smooth support around the tunnel perimeter (and, if required, also to the face) is a significant factor to minimize initial movement in the surrounding ground.
  • It is also essential to structurally close the supporting ring (shotcrete) as quickly as possible within one tunnel diameter from the advancing face.
  • The 3-dimensional stress redistribution around the tunnel depends on geometry and time. This must be considered carefully, particularly where multiple openings are planned. It will govern the progress of tunnelling with respect to stress redistribution, soilstructure interaction and curing of the shotcrete support.

Continuous (and, if feasible) symmetric excavation of drifts avoids inhomogeneities in stiffness of the initial lining, changing load conditions and, therefore, provides smooth stress redistribution in both, lining and the surrounding ground.

NATM is an observational method. Therefore monitoring (in-situ-measurements) of deformation within the ground and opening as well as stress development on and in the initial lining (shotcrete) is essential.

The success of execution of the NATM is based on three premises:

  • thoughtful, skilful design
  • skilled execution
  • competent supervision and interpretation of observation result

Typical support for NATM in unstable ground conditions

Typical elements of support

 

Tunnel Technology

1. What is "top heading" and "benching" in tunnel excavation?

Tunnel excavation consists of "top heading" - excavating and supporting the upper two-thirds of the tunnel - followed by "benching" - excavating and supporting (stabilizing) the lower one-third of the tunel

"Top heading" construction sequence consists of the  following:

- Holes are drilled in the top two-thirds of the tunnel and exposives are loaded and detonated in a carefully designed sequence to acieve the proper balance between sufficient breakage of excavated material and minimal damage to surrounding rock.

- Following the blast, the tunnel is ventilated to clear the explosion gases, and air quality measurements are taken to ensure safe return to the tunnel.

- The exposed top part of the tunnel arch("crown") and face are "scaled" (scraped off) using drill equiment or hand tools to remove loose rock. The crown area is then reinforced with rock bolts, rock dowels, or lattice girders (if needed), and shotcrete, creating a rock arch over the tunnel. The decision to use either bolts, dowels or lattice girders and the thickness of shotcrete (2-6 inches, plain concrete or reinforced with steel fibres) depends on the category of rock and the necessary support required.

"Benching" construction sequence consists of the following:

- First, the center portion (within 5-feet of each sidewall) of the lower one-third of the tunnel is drilled, blasted, and mucked out, following the same procedures as for the "top heading". The 5-foot spacings on both sides of the lower one-third of the tunnel ("side slashed") are left to act as buttreses and to prevent the blast pressure from damaging the retianing walls.

- Second, the "side slashes" are drilled, blasted, mucked out, and stabilized by rock bolts and shotcrete, corersponding to the ground support used for the "top heading"

2. What is a "round"?

The tunneling process is the excavation of the tunnel shape through the rock in small increments - each increment representing a "round". The "round" measures the forward advancement (in feet) of the excavation process, which consist of drill, blasting, ventilating, mucking and installing the support. A "cycle" is the time (in hours) to complete the "round". The quality of the rock determines how many feet can be extracted in each "round" and the amount time ("cycle") it takes to install the necessary support before a subsequent "round" can be excavated. 

Top


This homepage is presented by the Consultant Team

Any further question should be forwarded to Webmaster or Consultant Team

 


Progress To Date

By Figure
By Primavera



Tunnel Excavation
Record

By Number
By Figure
By Plan
By Chart




Monthly Progress

Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII



News and Events
Project
Public Media
Visitor List



Organization Charts

The Employer
The Consultant
The Contractors
Others



Consultant Office

List of Staff
Members Only



Project Information
Introduction
(MS-PowerPoint)
Project Map
Background
Major Features
Chronicle
Contract Packages
Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII
Natural Conditions
Socio-Economic Dev.



Public Relations
Site Map
Contact Us
Related Agencies
Link
FAQs
Knowledgebase
Guest Book



Our Gallery
Computer Graphics
Perspective
Vietnam
Introduction
Photo Selection



Around Project
Highway Network in
Vietnam
Large-scaledHighway
Projects in Central
of Vietnam



Tiếng Việt



Coordination