Package IA - Tunnel Civil Works: North Tunnel Section

Executing Agency
Ministry of Transport and Communication
Employer
Project Management Unit 85 (PMU 85)
Loans Under
JBIC-Japan Bank for International Cooperation
Consultant

Joint Ventuve of NIPPON KOEI CO., LTD. (Japan) and LOUIS BERGER INC. (USA) in association with TEDI (Vietnam)

Contractor

Package Data

  • Scope of Works

The construction works comprising the Contract Package-IA: North Tunnel Section, (Sta. 1+515.000 to Sta. 5+500.000) shall include:

(a) An approximately 3,857 meters long 2-lane main tunnel with 73.26m2 cross-section (Sta. 1+643.000 to Sta. 5+500.000);

(b) An approximately 3,857 meters long evacuation tunnel with 15.47m2 cross-section, parallel to the main tunnel;

(c) Two vehicular cross-passageways (one 19.65m long and one 21.65m long) with 15.47m2 cross-section, and seven pedestrian cross-passageways (three 21.65m long plus four 19.65m long) with 8.12m2 cross-section;

(d) A 1,810 meters long tunnel ventilation adit with 36.20m2 cross-section;

(e) Two 153 meters long each (main tunnel center-to-center), by-pass type electrostatic precipitator tunnels (north & central) with 57.69m2 cross-section;

(f) A 128 meters 2-lane tunnel approach (Sta. 1+515.000 - Sta. 1.643.000);

(g) An approximately 403 meters long access road to adit building;

(h) A 80m2, one-story substation structure (building only); and

(i) A north tunnel portal plaza and a ventilation adit portal plaza

 

 

Top

  • Major Works Quantity

No.

Description

Unit

Quantity

1.

Tunnel Excavation (Rock Type I-VI)

m3

551,234

2.

SN Rock Bolts (L = 2 ~ 12m)

pieces

41,713

3.

IBO Rock Bolts (2 ~ 6m)

pieces

8,747

4.

SWELLEX Rock Bolts (2 ~ 6m)

pieces

8,137

5.

Forepoling

pieces

8,500

6.

Consolidation Grout

ton

2,238

7.

PVC Drainage Pipe (ø 50 - 400mm)

m

11,233

8.

Tunnel Waterproofing Membrane (EVA 0.8mm)

m2

143,889

9.

Tunnel Lining Concrete t = 300mm

m3

41,300

10.

Structural Concrete in Tunnel

m3

23,265

11.

PC Concrete Pavement (t = 10, 20, 24cm)

m2

19,164

12.

Shotcrete t = 5 ~ 40cm

m2

218,415

13.

Wiremesh

m2

115,968

14.

Steel Ribs (H - 100, 175)

ton

824

Top

  • Milestones

The contract milestone of 48 months of contingency period:

No.

Work to be completed

Milestone

1.

All civil works in electrostatic precipitators

11 months prior to the completion of the whole works

2.

Concrete Lining and pavement in the main tunnel

6 months

3.

Concrete Wall of the raised walkway on the western side of the main tunnel (including cable ducts but excluding cover)

6 months

4.

Curb on the eastern side of main tunnel

6 months

5.

Ventilation Adit

3 months

This homepage is presented by the Consultant Team

Any further question should be forwarded to Webmaster or Consultant Team
 


Progress To Date

By Figure
By Primavera



Tunnel Excavation
Record

By Number
By Figure
By Plan
By Chart




Monthly Progress

Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII



News and Events
Project
Public Media
Visitor List



Organization Charts

The Employer
The Consultant
The Contractors
Others



Consultant Office

List of Staff
Members Only



Project Information
Introduction
(MS-PowerPoint)
Project Map
Background
Major Features
Chronicle
Contract Packages
Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII
Natural Conditions
Socio-Economic Dev.



Public Relations
Site Map
Contact Us
Related Agencies
Link
FAQs
Knowledgebase
Guest Book



Our Gallery
Computer Graphics
Perspective
Vietnam
Introduction
Photo Selection



Around Project
Highway Network in
Vietnam
Large-scaledHighway
Projects in Central
of Vietnam



Tiếng Việt



Coordination