Construction
Supervision
Summary
The
whole 6 bridges on the route was completed in
construction work. Most of construction work was
finished and taking-over celebration was held on 4
January 2005 to hand-over to Hamadeco. However,
there are some minor works must be carried out to
complete such as:
Bridge
works:
1.
Top surface of piers and abutments of all bridges
must be cleaned
2.
Around rubber part of expansion joints on bridge
must be filled by water proofing glue
3.
Protection around A1 (down stream side) of Bridge
No.3, crackers on mortar riprap surface of
protection around A1&A2 of Bridge No.4 and water
drainage ditches in front of A1 of Bridge No.6 must
be repaired.
4.
Stair surface of vertical ditch in protection around
A1 of Bridge No.5 and A1 of Bridge No.7 must be
repaired because of peeling off.
5.
Many handrail sections of Bridge No.5 and Bridge
No.6 must be repaired because they are not fix
6.
The Contractor PK2B shall discuss with the
Contractor PK3 to repair some positions of
electrical post where handrail paint was peeled off.
Road
works:
7.
Section from PK2B’s border to Bridge No.2:
*
Some broken curbs must be repaired. The Contractor
PK2B shall discuss with the Contractor PK3 to
reinstall some rail sections that was unbind.
*
Ditch in mountainside has not executed yet.
*
Slope protection in downstream side must be repaired
and grow grass how to be appropriate with landscape
of tunnel portal.
8.
Section from Bridge No.2 to Bridge No.3:
*
Slope of mountain near bridge No.2 was eroded
heavily on surface. The Contractor PK2B are
requested to prepare drawing (investigation and
design) to submit Consultant to revise and modify
strictly.
*
Ditch in sea side must be installed in addition.
*
Some broken ditch in mountain side must be repaired.
*
Stone on surface of cut-slope must be cleaned.
*
Berms on cut-slope must be repaired.
*
The end section from berm, which was broken, must be
repaired strictly.
*
The PMU85 shall discuss with local administrator to
prevent rushing wood from the top of mountain down
to road leading to damage some construction work
items
*
Some drilling holes for asphalt sample must be
filled
*
Curb section closed A2 of Bridge No.2 down stream
must be added
9.
Section from Bridge No.3 to Bridge No.4:
*
Top of retaining wall closed A2 of Bridge No.3 must
be casting concrete to flat and to reinforce for
precautionary guardrail
*
Stream under Bridge No.3 must be cleared off.
*
Vertical ditch (mountain side) from Bridge No.3 must
be continued construction. Closed this position,
excavation of mountain footing must be stopped
immediately to avoid damage of slope protection.
*
The Contractor PK2B shall grow up grass in road
shoulder in mountain side
*
Drainage ditch on slope of culver km9+100 up stream
side to installed ditch must be continued
construction.
*
Vertical ditch (mountain side) from culver km9+115
to installed ditch Danang side must be continued
construction. In this section, the collection ditch
shall be added to collect water to vertical ditch.
*
Berms on cut-slope must be repaired.
*
Top soil on slope is higher than reinforcing mortar
riprap must be flatted and grow grass on surface.
*
Vertical ditch, which connect berms on cut-slope,
must be added as previous checking minutes.
*
Curb slits which closed A1 of Bridge No.4 down
stream must be banded
10.
Section from Bridge No.4 to Bridge No.5:
*
Curb section closed A2 of Bridge No.4 down stream
must be added.
11.
Section from No.5 to Bridge No.6:
*
Fours drainage ditch on cut-slope must be added
under Engineer’s instruction
*
Vertical ditch in sea side must be added.
*
Curbs downstream of A1 of Bridge No.5 must be
banded.
*
Backfill; behind side ditch must be completed
12.
Section from Bridge No.6 to Bridge No.7:
*
A section of curb, which was destroyed by
households, must be recover. From this position to
slope footing must be compacted tightly and trend to
vertical ditch to collect water to ditch.
*
Some curb sections are not regular must be repaired
*
Stone on slope must be moved all.
*
A vertical ditch section where underground water run
through to road must be treated.
*
Vertical ditch in sea side must be added
*
Backfill behind side ditch must be completed
13.
Section Bridge No.7 to Toll Plaza:
*
Risky stone on slope must be removed.
*
Broken vertical because of poor quality must be
repaired.
*
Connection road upstream of sub road must be
completed km11+260
*
Backfill behind side ditch must be completed
*
Upstream and downstream of culver km11+50 must be
repaired (cut slope, facing stone for slope and
install berm to run water from vertical ditch to
culver gate)
*
Inside and outside round culver km11+290 must be
cleaned (soil inside must be removed)
*
Crackers in connection point between asphalt
concrete road and cement concrete road must be
repaired by using cutter to create connection joint
2cm wide and to fill mastic and sand.
*
Concrete road surface and slope protection in toll
plaza area must be cleaned.
*
Floor and wall in toll box must be cleaned. Lock of
gates in toll plaza must be repaired. Growing up
grass and died trees shall be carried out in toll
plaza area. Equipment in toll plaza must be tested
before taking over.
*
Installation extinguisher
*
Calculation sheet of structure of Toll Plaza
*
Pipe culver, km11+660 up and down stream must be
repaired; slope in upstream must be reinforced.
*
Vertical ditch wall must be backfilled and compacted
tightly.
14.
Section from toll plaza to the end of alignment:
*
Vertical ditch must be repaired.
*
Behind of vertical ditch wall must be backfilled and
compacted tightly.
*
Backfill behind side ditch must be completed
15.
Presently, the Contractor PK2B have put km post
without submission of drawing and installed position
to Engineer. The Contractor PK2B are requested to
submit soon for approval before taking over.
16.
Sections, which were added handrail, were approval
by Engineer in basically, the Contractor are
requested to deploy soon.
17.
Addition of reflection steel plate for all installed
guardrail sections
18.
Plant trees along connection road
19.
Addition of speed limit sign at both sides of Toll
Plaza (5km/h)
20.
Right off way post must be completed