Project Information > Contract Packages

Package IIA - Road and Bridge Works: Lang Co Bridge Section

Executing Agency Ministry of Transport and Communication
Employer Project Management Unit 85 (PMU 85)
Loans Under JBIC-Japan Bank for International Cooperation
Consultant

Joint Ventuve of NIPPON KOEI CO., LTD. (Japan) and LOUIS BERGER INC. (USA) in association with TEDI (Vietnam)

Contractor Joint Venture of Thang Long and Truong Son (Vietnam)

Package Data

  • Scope of Works

Package IIA: Lang Co Bridge Section (Sta. -1+865.000 to Sta. 1+515.000) shall include construction of:

(a) Lang Co Bridge, 876.390 meters total length;

(b) Two lane roadway, 782.610 meters total length;

(c) A northern toll plaza; and

(d) Construction of 187m2 are enclosed car port

 

Top

  • Major Works Quantity

No.

Description

Unit

Quantity

1.

Embankment excavation

m3

245

2.

Borrow material

m3

76,458

3.

Structural excavation (on ground)

m3

6,467

4.

Structural excavation (underwater)

m3

5,489

5.

Backfilling

m3

4,547

6.

Sub-base courses

m3

7,665

7.

Base courses

m3

4,002

8.

Asphalt concrete surface 5cm

m2

12,448

9.

Asphalt concrete surface 7cm

m2

9,712

10.

Asphalt concrete binder courses 6cm

m2

12,282

11.

Toll plaza

 

 

12.

Concrete class B

m3

12,745

13.

Concrete class C

m3

1,157

14.

Concrete class E-L

m3

194

15.

Concrete class P

m3

31

16.

PC girder 33m

each

130

17.

CIP

m

13,150

18.

Steel bar

kg

35,619

19.

Frame steel

kg

2,931

20.

Hand rail

m

1765

21.

Laminated elastomeric bearing pads

each

260

22.

Movement joints

LM

130

  • Milestones

No.

Work to be completed

Milestone

1

Preparation Works

120 days

2

Bridge work - Substructure

554 days

3

Bridge work - Superstructure

729 days

4

Approach road

779 days

5

Toll plaza

152 days

This homepage is presented by the Consultant Team

Any further question should be forwarded to Webmaster or Consultant Team
 


Progress To Date

By Figure
By Primavera



Tunnel Excavation
Record

By Number
By Figure
By Plan
By Chart




Monthly Progress

Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII



News and Events
Project
Public Media
Visitor List



Organization Charts

The Employer
The Consultant
The Contractors
Others



Consultant Office

List of Staff
Members Only



Project Information
Introduction
(MS-PowerPoint)
Project Map
Background
Major Features
Chronicle
Contract Packages
Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII
Natural Conditions
Socio-Economic Dev.



Public Relations
Site Map
Contact Us
Related Agencies
Link
FAQs
Knowledgebase
Guest Book



Our Gallery
Computer Graphics
Perspective
Vietnam
Introduction
Photo Selection



Around Project
Highway Network in
Vietnam
Large-scaledHighway
Projects in Central
of Vietnam



Tiếng Việt



Coordination