As of May 31, 2005

Physical Progress

Contractor

ITOCHU Corporation

Commencement of the Works

18 February 2005

Contract Period 17 August 2005 (180 days)
Time Elapsed (days) 40 of 180 days (22.22%)

Progress

  5 vehicles delivered on 25 May 2005

Photographs

Top

Construction Supervision

Item No. 1/Tunnel Superintendent Staff Car (2 units), Item No. 2/Patrol Car (1 unit), Item No. 3/Road maintenance Vehicle (Van Type) (2 units) and Item No. 4/Road Maintenance Vehicle (Station Wagon Type) were finished manufacturing by Toyota on 3rd week of March, and then transferred to the body manufacturer’s factory to mount necessary accessories on them. It was expected that Item No. 1, 2 and 3 would be ready to ship on and around the middle of April. As for Item No. 4, it depends on the approval of the display drawing.

Other items were under production in each manufacturer as scheduled.

Top


This homepage is presented by the Consultant Team

Any further question should be forwarded to Webmaster or Consultant Team

 

 


Progress To Date

By Figure
By Primavera



Tunnel Excavation
Record

By Number
By Figure
By Plan
By Chart




Monthly Progress

Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII



News and Events
Project
Public Media
Visitor List



Organization Charts

The Employer
The Consultant
The Contractors
Others



Consultant Office

List of Staff
Members Only



Project Information
Introduction
(MS-PowerPoint)
Project Map
Background
Major Features
Chronicle
Contract Packages
Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII
Natural Conditions
Socio-Economic Dev.



Public Relations
Site Map
Contact Us
Related Agencies
Link
FAQs
Knowledgebase
Guest Book



Our Gallery
Computer Graphics
Perspective
Vietnam
Introduction
Photo Selection



Around Project
Highway Network in
Vietnam
Large-scaledHighway
Projects in Central
of Vietnam



Tiếng Việt



Coordination