|
The
pre-feasibility studies for the Project were completed by Transport
Engineering Design Incorporation (TEDI) in April 1996, and by the
Express Highway Research Foundation of Japan in June 1996. Upon request
of the Government of the Socialist Republic of Vietnam, the Government
of Japan through the former Overseas Economic Cooperation Fund (OECF,
now renamed Japan Bank for International Cooperation - JBIC) decided
to provide a loan to finance the construction of the Project. The
first loan agreement between the two governments was concluded on
March 26, 1997 and the second loan agreement on March 30,1999.
The
executing agency of the Project is the Project Management Unit No.85
(PMU85) under the Ministry of Transport (MOT) of the Government of
the Socialist Republic of Vietnam. On December 12, 1997, PMU85 signed
a contract for consulting engineering services for the Hai Van Pass
Tunnel Construction Project, with the joint-venture of Nippon Koei
Co., Ltd., Japan and Louis Berger International Inc., USA, in association
with Transport Engineering Design Incorporation (TEDI), Vietnam (the
Consultant). The Consulting Services consist of the following five
components:
1)
Special Survey
2)
Detailed Design
3)
Contract Tendering Assistance
4)
Construction Supervision
5)
Training and Technology Transfer
Following
the issuance of the Notice to Proceed on January 2, 1998, the Consultant
officially commenced the Services on January 20, 1998.
The
Special Survey, the major objective of which is to select the most
desirable route of the Project through detailed comparison of route
alternatives, was completed with the submission of the Special Survey
Report on April 23, 1998.
The
Detailed Design commenced at the end of February 1998, and was substantially
completed with the transmittal of the draft bidding documents for
five contract packages by the end of July 1999. The Services during
the Tendering Stage were commenced with the assistance for prequalification
evaluation for Contract Package-I: Tunnel Civil Works conducted in
June 1999. Tendering for Packages IA and IB was completed with the
signing of Contracts on August 17, 2000 and the Project entered the
construction stage in parallel with the tendering for the remaining
packages.
Events/Activities
|
Date/Period
|
Carried
out by
|
Prime
Minister's Decree on Project Study |
Mar.
22, 1994 (22/CP)
|
|
Pre
Feasibility Study |
May
1996
|
Express
Highway Research Foundation of Japan
|
Special
Survey |
Jan.
- Apr. 1998
|
NK/LBII/TEDI
|
Prime
Minister's Investment Decision |
Sep.
30, 1998 (905/QD-TTg)
|
|
Detailed
Design |
Feb.
1998 - Jul. 1999
|
NK/LBII/TEDI
|
Package
1A&1B, Tunnel Civil Works
|
PQ
Notice |
Jun.
6, 1999
|
PMU85
|
PQ
Evaluation |
Jun.
11 - 22, 1999
|
PMU85
& Consultant
|
JBIC
Approval of PQ Evaluation Result |
Sep.
11, 1999
|
JBIC
|
Bidding
Invitation |
Dec.
4, 1999
|
PMU85
|
Bid
Opening |
Feb.
29, 2000
|
PMU85
& Consultant
|
Bid
Evaluation |
Mar.
1 - 24, 2000
|
PMU85
& Consultant
|
JBIC
Approval of Bid Evaluation Result |
Aug.
11, 2000
|
JBIC
|
Contract
Negotiation |
Aug.
12 - 16, 2000
|
PMU85,
Contractors & Consultant
|
Contract
Signing |
Aug.
17, 2000
|
PMU85
& Contractors
|
Notice
to proceed |
Sep.
1, 2000
|
PMU
85
|
Commencement
of Works |
Oct.
1, 2000
|
|
Package
2A, Lang Co Bridge Section & 2B, Southern Highway Section
|
PQ
Notice |
Dec.
8, 1999
|
PMU85
|
PQ
Evaluation |
Jan.18
- Feb 13, 2000
|
PMU85,
Vinh
|
JBIC
Approval of PQ Evaluation Result |
May
29, 2000 (2000/HAN(1A)-070, 071)
|
JBIC
|
Bidding
Invitation |
Oct.
12, 2000
|
At
Danang City
|
Bid
Opening |
Dec.
12, 2000
|
At
Vinh City
|
Bid
Evaluation |
Dec.
12 - 23, 2000
|
At
Vinh City
|
JBIC
Approval of Bid Evaluation Result |
March
27, 2001
|
JBIC
|
Contract
Negotiation |
April
23 ~ 25, 2001 (PKIIA)
May
20 ~ 23, 2001 (PKIIB)
|
Vinh
|
Contract
Signing |
May
3, 2001 (PKIIA)
May
28, 2001 (PKIIB)
|
Hanoi
Vinh
|
Notice
to Proceed PKIIA / PKIIB |
June
1 / June 26
|
|
Commencement
of works PKIIA / PKIIB |
July
1 / July 26
|
|
Package
3, Electrical Works
|
PQ
Notice |
June
200
|
PMU85
|
PQ
Evaluation |
July
17 - 25, 2000
|
PMU85
& Consultant, Vinh
|
JBIC
Approval of PQ Evaluation Result |
Nov.
3, 2000 (HAN/2000 - 125)
|
JBIC
|
Bidding
Invitation |
April
10, 2001
|
Vinh
|
Pre-bid
Conference |
April
18 ~ 19, 2001
|
Emp./Engineer's
Office
|
Bid
Opening |
June
26, 2001
|
Vinh
|
Bid
Evaluation |
June
27 - July 28, 2001
|
PMU85
Vinh
|
Package
4, Mechanical Works
|
PQ
Notice |
June
1, 2000
|
PMU85
|
PQ
Evaluation |
July
17-25, 2000
|
PMU85
& Consultant, Vinh
|
JBIC
Approval of PQ Evaluation Result |
Oct.
16, 2000
|
JBIC
|
Bidding
Invitation |
April
10, 2001
|
Vinh
|
Pre-bid
Conference |
April
18 ~ 19, 2001
|
Emp./Engineer's
Office
|
Bid
Opening |
June
26, 2001
|
Vinh
|
Bid
Evaluation |
June
27 ~ July 11, 2001
|
PMU85
Vinh
|
JBIC
Approval of Bid Evaluation Result |
Nov.
15, 01 (HAN/2001-139)
|
JBIC
|
Contract
Negotiation |
Jan.
12 ~ Jan. 15, 02
|
PMU85
Vinh
|
Contract
Signing |
Jan.
18, 02
|
|
Notice
to proceed |
Feb.
12, 02
|
|
Commencement
of Works |
Mar.
13, 2002
|
|
Package
5, 110/22KV Substation and Transmission Line
|
PQ
Notice |
Aug.
11, 1999
|
PMU85
|
PQ
Evaluation |
Oct.
2-10, 1999
|
PMU85
& Consultant
|
JBIC
Approval of PQ Evaluation Result |
Oct.
28, 1999 (HAN/99-126)
|
JBIC
|
Bidding
Invitation |
Dec.
13, 1999
|
PMU85,
Vinh
|
Bid
Opening |
Feb.
28, 2000
|
PMU
85 & Consultant, Vinh
|
Bid
Evaluation |
March
1- 22, 2000
|
PMU85
& Consultant, Vinh
|
JBIC
Approval of Bid Evaluation Result |
July
24, 2001
|
|
Contract
Negotiation |
Sep.
10 ~ 15, 2001
|
PMU85
Vinh
|
Contract
Signing |
Sep.
15, 2001
|
PMU85
Vinh
|
Notice
to Proceed |
Oct.
18, 2001
|
|
Commencement
of Works |
Dec.
21,, 2001
|
|
Package
6, Procurement of Maintenance Vehicles
|
Bidding
Submission for Approval |
Feb.
22, 2001
|
|
Package
7, Infrastructure for Resettlement Areas
|
Distribution
of Bidding Documents |
5
to 8 March, 2001
|
|
Pre-Bid
Meeting and Site Visit |
15
to 16 March, 2001
|
|
Deadline
for Questionnaires |
March
19, 2001
|
|
Deadline
for Answering of Questionnaires |
April
02, 2001
|
|
Submission
of Bids |
08:00
a.m., April 9, 2001
|
|
Bid
Opening |
09:00
a.m., April 9, 2001
|
|
Bid
Evaluation |
From
April 12 ~ 21, 2001
|
|
JBIC
Approval of Bid Evaluation Result |
June
5, 2001
|
|
Contract
Negotiation |
June
7, 2001
|
|
Contract
Signing |
June 9, 2001
|
|
Notice
to proceed |
August
1, 2001
|
|
Commencement
of Works |
August
31, 2001
|
|
Top
This
homepage is presented by the Consultant Team
Any
further question should be forwarded to Webmaster
or Consultant Team
|
|
Progress To Date
By
Figure
By
Primavera

Tunnel
Excavation
Record
By
Number
By
Figure
 By
Plan
 By
Chart

Monthly
Progress
Package
IA
Package
IB
Package
IIA
Package
IIB
Package
III
Package
IV
Package
V
Package
VI
Package
VII

News
and Events
Project
Public
Media
Visitor
List

Organization
Charts
The
Employer
The
Consultant
The
Contractors
Others

Consultant
Office
List
of Staff
Members
Only

Project
Information
Introduction
(MS-PowerPoint)
Project
Map
Background
Major
Features
Chronicle
Contract
Packages
 Package
IA
 Package
IB
 Package
IIA
 Package
IIB
 Package
III
 Package
IV
 Package
V
 Package
VI
 Package
VII
Natural
Conditions
Socio-Economic
Dev.

Public
Relations
Site
Map
Contact
Us
Related
Agencies
Link
FAQs
Knowledgebase
Guest
Book

Our
Gallery
Computer
Graphics
Perspective
Vietnam
 Introduction
 Photo
Selection

Around
Project
Highway
Network in
Vietnam
Large-scaledHighway
Projects
in Central
of
Vietnam

Tiếng
Việt

Coordination
|