Chronicle of the Consulting Services

The pre-feasibility studies for the Project were completed by Transport Engineering Design Incorporation (TEDI) in April 1996, and by the Express Highway Research Foundation of Japan in June 1996. Upon request of the Government of the Socialist Republic of Vietnam, the Government of Japan through the former Overseas Economic Cooperation Fund (OECF, now renamed Japan Bank for International Cooperation - JBIC) decided to provide a loan to finance the construction of the Project. The first loan agreement between the two governments was concluded on March 26, 1997 and the second loan agreement on March 30,1999.

The executing agency of the Project is the Project Management Unit No.85 (PMU85) under the Ministry of Transport (MOT) of the Government of the Socialist Republic of Vietnam. On December 12, 1997, PMU85 signed a contract for consulting engineering services for the Hai Van Pass Tunnel Construction Project, with the joint-venture of Nippon Koei Co., Ltd., Japan and Louis Berger International Inc., USA, in association with Transport Engineering Design Incorporation (TEDI), Vietnam (the Consultant). The Consulting Services consist of the following five components:

1) Special Survey

2) Detailed Design

3) Contract Tendering Assistance

4) Construction Supervision

5) Training and Technology Transfer

Following the issuance of the Notice to Proceed on January 2, 1998, the Consultant officially commenced the Services on January 20, 1998.

The Special Survey, the major objective of which is to select the most desirable route of the Project through detailed comparison of route alternatives, was completed with the submission of the Special Survey Report on April 23, 1998.

The Detailed Design commenced at the end of February 1998, and was substantially completed with the transmittal of the draft bidding documents for five contract packages by the end of July 1999. The Services during the Tendering Stage were commenced with the assistance for prequalification evaluation for Contract Package-I: Tunnel Civil Works conducted in June 1999. Tendering for Packages IA and IB was completed with the signing of Contracts on August 17, 2000 and the Project entered the construction stage in parallel with the tendering for the remaining packages.

Top

History of the Project

Events/Activities

Date/Period

Carried out by

Prime Minister's Decree on Project Study
Mar. 22, 1994 (22/CP)
Pre Feasibility Study
May 1996
Express Highway Research Foundation of Japan
Special Survey
Jan. - Apr. 1998
NK/LBII/TEDI
Prime Minister's Investment Decision
Sep. 30, 1998 (905/QD-TTg)
Detailed Design
Feb. 1998 - Jul. 1999
NK/LBII/TEDI

Package 1A&1B, Tunnel Civil Works

PQ Notice
Jun. 6, 1999
PMU85
PQ Evaluation
Jun. 11 - 22, 1999
PMU85 & Consultant
JBIC Approval of PQ Evaluation Result
Sep. 11, 1999
JBIC
Bidding Invitation
Dec. 4, 1999
PMU85
Bid Opening
Feb. 29, 2000
PMU85 & Consultant
Bid Evaluation
Mar. 1 - 24, 2000
PMU85 & Consultant
JBIC Approval of Bid Evaluation Result
Aug. 11, 2000
JBIC
Contract Negotiation
Aug. 12 - 16, 2000
PMU85, Contractors & Consultant
Contract Signing
Aug. 17, 2000
PMU85 & Contractors
Notice to proceed
Sep. 1, 2000
PMU 85
Commencement of Works
Oct. 1, 2000

Package 2A, Lang Co Bridge Section & 2B, Southern Highway Section

PQ Notice
Dec. 8, 1999
PMU85
PQ Evaluation
Jan.18 - Feb 13, 2000
PMU85, Vinh
JBIC Approval of PQ Evaluation Result
May 29, 2000 (2000/HAN(1A)-070, 071)
JBIC
Bidding Invitation
Oct. 12, 2000
At Danang City
Bid Opening
Dec. 12, 2000
At Vinh City
Bid Evaluation
Dec. 12 - 23, 2000
At Vinh City
JBIC Approval of Bid Evaluation Result
March 27, 2001
JBIC
Contract Negotiation

April 23 ~ 25, 2001 (PKIIA)

May 20 ~ 23, 2001 (PKIIB)

Vinh
Contract Signing

May 3, 2001 (PKIIA)

May 28, 2001 (PKIIB)

Hanoi

Vinh

Notice to Proceed PKIIA / PKIIB
June 1 / June 26
Commencement of works PKIIA / PKIIB
July 1 / July 26

Package 3, Electrical Works

PQ Notice
June 200
PMU85
PQ Evaluation
July 17 - 25, 2000
PMU85 & Consultant, Vinh
JBIC Approval of PQ Evaluation Result
Nov. 3, 2000 (HAN/2000 - 125)
JBIC
Bidding Invitation
April 10, 2001
Vinh
Pre-bid Conference
April 18 ~ 19, 2001
Emp./Engineer's Office
Bid Opening
June 26, 2001
Vinh
Bid Evaluation
June 27 - July 28, 2001
PMU85 Vinh

Package 4, Mechanical Works

PQ Notice
June 1, 2000
PMU85
PQ Evaluation
July 17-25, 2000
PMU85 & Consultant, Vinh
JBIC Approval of PQ Evaluation Result
Oct. 16, 2000
JBIC
Bidding Invitation
April 10, 2001
Vinh
Pre-bid Conference
April 18 ~ 19, 2001
Emp./Engineer's Office
Bid Opening
June 26, 2001
Vinh
Bid Evaluation
June 27 ~ July 11, 2001
PMU85 Vinh
JBIC Approval of Bid Evaluation Result
Nov. 15, 01 (HAN/2001-139)
JBIC
Contract Negotiation
Jan. 12 ~ Jan. 15, 02
PMU85 Vinh
Contract Signing
Jan. 18, 02
Notice to proceed
Feb. 12, 02
Commencement of Works
Mar. 13, 2002

Package 5, 110/22KV Substation and Transmission Line

PQ Notice
Aug. 11, 1999
PMU85
PQ Evaluation
Oct. 2-10, 1999
PMU85 & Consultant
JBIC Approval of PQ Evaluation Result
Oct. 28, 1999 (HAN/99-126)
JBIC
Bidding Invitation
Dec. 13, 1999
PMU85, Vinh
Bid Opening
Feb. 28, 2000
PMU 85 & Consultant, Vinh
Bid Evaluation
March 1- 22, 2000
PMU85 & Consultant, Vinh
JBIC Approval of Bid Evaluation Result
July 24, 2001
Contract Negotiation
Sep. 10 ~ 15, 2001
PMU85 Vinh
Contract Signing
Sep. 15, 2001
PMU85 Vinh
Notice to Proceed
Oct. 18, 2001
Commencement of Works
Dec. 21,, 2001

Package 6, Procurement of Maintenance Vehicles

Bidding Submission for Approval
Feb. 22, 2001

Package 7, Infrastructure for Resettlement Areas

Distribution of Bidding Documents
5 to 8 March, 2001
Pre-Bid Meeting and Site Visit
15 to 16 March, 2001
Deadline for Questionnaires
March 19, 2001
Deadline for Answering of Questionnaires
April 02, 2001
Submission of Bids
08:00 a.m., April 9, 2001
Bid Opening
09:00 a.m., April 9, 2001
Bid Evaluation
From April 12 ~ 21, 2001
JBIC Approval of Bid Evaluation Result
June 5, 2001
Contract Negotiation
June 7, 2001
Contract Signing
June 9, 2001
Notice to proceed
August 1, 2001
Commencement of Works
August 31, 2001

 

Top


This homepage is presented by the Consultant Team

Any further question should be forwarded to Webmaster or Consultant Team

 

 


Progress To Date

By Figure
By Primavera



Tunnel Excavation
Record

By Number
By Figure
By Plan
By Chart




Monthly Progress

Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII



News and Events
Project
Public Media
Visitor List



Organization Charts

The Employer
The Consultant
The Contractors
Others



Consultant Office

List of Staff
Members Only



Project Information
Introduction
(MS-PowerPoint)
Project Map
Background
Major Features
Chronicle
Contract Packages
Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII
Natural Conditions
Socio-Economic Dev.



Public Relations
Site Map
Contact Us
Related Agencies
Link
FAQs
Knowledgebase
Guest Book



Our Gallery
Computer Graphics
Perspective
Vietnam
Introduction
Photo Selection



Around Project
Highway Network in
Vietnam
Large-scaledHighway
Projects in Central
of Vietnam



Tiếng Việt



Coordination