Welcome to Our Site!
 

 

Project Information >Contract Packages

Package IB - Tunnel Civil Works: South Tunnel Section

Executing Agency
Ministry of Transport and Communication
Employer
Project Management Unit 85 (PMU 85)
Loans Under
JBIC-Japan Bank for International Cooperation
Consultant

Joint Ventuve of NIPPON KOEI CO., LTD. (Japan) and LOUIS BERGER INC. (USA) in association with TEDI (Vietnam)

Contractor

Package Data

  • Scope of Works

The construction works comprising the Package-IB: South Tunnel Section shall include: (Sta. 5+500.000 to Sta. 8+125.000)

(a) An approximately 2,417 meters long 2-lane main tunnel with 73.26m2 cross-section (Sta. 5+500.000 to Sta. 7+917.000);

(b) An approximately 2,429 meters long evacuation tunnel with 15.47m2 cross-section, parallel to the main tunnel;

(c) Two 19.65 meters long vehicular cross-passageways with 15.47m2 cross-section, and four pedestrian cross-passageways (two 21.65m long plus two 19.65 meter long) with 8.12m2 cross-section;

(d) A 153 meters long (main tunnel center-to-center) by-pass type electrostatic precipitator tunnels (south) with 57.69m2 cross-section;

(e) A 208 meters 2-lane tunnel approach (Sta. 7+917.000 - Sta. 8+125.000);

(f) An approximately 817 meters long access road to high water reservoir;

(g) A 1,400m2, one-story, vehicular maintenance building;

(h) A 58.45 meters long, 2-lane, 2-span (25.08m and 33.37m) post-tensioned girder bridge (Sta. 8+044.275 - Sta. 8+102.725); and

(i) A south tunnel portal plaza.

 

 

  • Major Works Quantity

No

Description

Unit

Quantity

1

Main Tunnel

Length

m

2417.00

Width

m

11.90

Height

m

7.50

Internal Area

m2

73.26

2

Evacuation Tunnel

Length

m

2429.00

Width

m

4.70

Height

m

3.80

Internal Area

m2

15.47

3

Electrostatic Precipitator

Length

m

153.00

Width

m

10.20

Height

m

6.70

Internal Area

m2

57.69

4

Pedestrian Cross Passage

Number of Tunnel

no

4.00

Total Length

m

78.60

Length per Tunnel

m

21.65 (19.65)

Width

m

2.80

Height

m

3.20

Internal Area

m2

8.12

5

Vehicular Cross Passage

Number of Tunnel

no

2.00

Total Length

m

39.30

Length per Tunnel

m

19.65

Width

m

4.70

Height

m

3.80

Internal Area

m2

15.47

6

Bridge and Road

Bridge Length

m

58.45

Road Length

m

1025.00

7

Total of Main Quantity

Tunnel Excavation

m3

290793.00

Excavation

m3

313142.00

Concrete

m3

43941.00

All Type of Bolt

no

32860.00

Shotcrete

m3

12979.00

Waterproofing

m2

69679.00

8

Works Value

27.9 millions VND

 

  • Milestones

The contract milestone of 48 months of contingency period:

No.

Work to be completed

Milestone

1

All civil works in electrostatic Precipitator

11 months prior to the completion of whole Works

2

Concrete lining and pavement in the main tunnel

6 months

3

Concrete wall of the raised walkway on the western side of the main tunnel (including cable ducts but excluding cover)

6 months

4

Curb on the eastern side of the main tunnel

6 Months

This homepage is presented by the Consultant Team

Any further question should be forwarded to Webmaster or Consultant Team

 

 


Progress To Date

By Figure
By Primavera



Tunnel Excavation
Record

By Number
By Figure
By Plan
By Chart




Monthly Progress

Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII



News and Events
Project
Public Media
Visitor List



Organization Charts

The Employer
The Consultant
The Contractors
Others



Consultant Office

List of Staff
Members Only



Project Information
Introduction
(MS-PowerPoint)
Project Map
Background
Major Features
Chronicle
Contract Packages
Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII
Natural Conditions
Socio-Economic Dev.



Public Relations
Site Map
Contact Us
Related Agencies
Link
FAQs
Knowledgebase
Guest Book



Our Gallery
Computer Graphics
Perspective
Vietnam
Introduction
Photo Selection



Around Project
Highway Network in
Vietnam
Large-scaledHighway
Projects in Central
of Vietnam



Tiếng Việt



Coordination