As of August 31,2004 

Physical Progress

Contractor

JV of ABB, Kinden and Vinaincon

Commencement of the Works

21 December 2001

Contract period

540 days (Until June 20, 2003)

Time Elapsed (days)

910 of 540 (168.5%) Extended from June 20, 2003

Progress

 

 

Completed

Photographs

Top

Construction Supervision

A major milestone was achieved with the energising of the transmission line and Hai Van high voltage substation on the 30 June for a successful 72 hour test energisation. Over the 72 hour period the 110kV GIS, 22kV GIS, the main power and auxiliary transformers were energised from Lien Chieu substation. The operation and synchronisation of the diesel generators to the grid was also demonstrated. The synchronising of the generators with the network when the network is re-energised after an outage is still to be done. It requires switching on and off and on again of the 110kV transmission line.

Snag lists of items to be adjusted, re-set or otherwise corrected were prepared in coordination with Engineer, PTC No. 2 and Load Dispatch Centre (A3). By the end of July all items had been cleared with the exception of CBFP relaying to be reset in Lien Chieu substation when another shut down can be arranged and synchronising of the generators to the network when generators are running. A important item that was outstanding was the transmission line differential protection inter-tripping and that was successfully completed on 1 August.

Contractor completed and delivered all the As- Built documentation required by contract in July. This included as-built drawings, and Operations and Maintenance manuals.

Permanent energisation (power supply) service will be carried out when a number of issues relating to operations and contract to pay for power consumption are resolved. It is intended to have the Hai Van substation permanently energised as soon as possible. SITOC inspection was carried out before and during test energisation.

On Site Training was provided by the Contractors staff from 14th to the 26th June at the OCC.   The approved courses covered all the PKV works including 110kV GIS, 22kV GIS, LV equipment, diesel generators and MicroSCADA

Top


This homepage is presented by the Consultant Team

Any further question should be forwarded to Webmaster or Consultant Team

 

 


Progress To Date

By Figure
By Primavera



Tunnel Excavation
Record

By Number
By Figure
By Plan
By Chart




Monthly Progress

Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII



News and Events
Project
Public Media
Visitor List



Organization Charts

The Employer
The Consultant
The Contractors
Others



Consultant Office

List of Staff
Members Only



Project Information
Introduction
(MS-PowerPoint)
Project Map
Background
Major Features
Chronicle
Contract Packages
Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII
Natural Conditions
Socio-Economic Dev.



Public Relations
Site Map
Contact Us
Related Agencies
Link
FAQs
Knowledgebase
Guest Book



Our Gallery
Computer Graphics
Perspective
Vietnam
Introduction
Photo Selection



Around Project
Highway Network in
Vietnam
Large-scaledHighway
Projects in Central
of Vietnam



Tiếng Việt



Coordination