Welcome to Our Site!
 

 

Progress Report > Package IV - Mechanical Works

Physical Progress | Photographs | Construction Supervision

As of May 31 , 2005

Physical Progress

Contractor

Matsushita - Itochu Consortium

Commencement of the Works

13 March 2002

Contract period 1080 days (Until March 12, 2005)
Time Elapsed (days) 1130 of 1080 (104.53%) Remaining 14 days

Progress

 
  Mainly system commissioning

Photographs

Waterproofing for air duct separation wall at EP1
Air duct & entrance door of EP3
EP fan & air duct of EP3
Duct & nozzle of EP3
Exhaust fan motor
Measuring ventilation air velocity
Emergency call & fire fighting niche door
Fire fighting equipment in the niche
Emergency response training
Electric barrier at north portal
Installing ladder
Ladder of chimney
Paving around VAB
Fixed point view

 

Top

Construction Supervision

Summary

Up to 31 May 2005 the system were completed for operation.

Water Supply and Treatment System:

1

Intake Reservoir

10m3 with level sensing switch (H, LL)

2

Centrifugal Pump

4.0m/h x 122mH, 3ph-415V x 3.0kW x 2 sets

3

Water Treatment System

Multi-media Filter (Sand Filter)

UV Disinfector

Anthrazite Filter

Chlorine Dosing System

4

Roof Tank

5m3 (2 x 2.5m3) with 2 x level sensing switch (HH, H, L, LL)

5

High Level Reservoir

100m3(2 x 50m3) with 2 x level sensing switch (HH, H, L, LL)

6

Drill Shaft

About 240m long piping from HLR to fire suppression  pipe of the main tunnel including about 64m long down pipe

7

Fire Suppression Pipe

Approx.6,330m long pipe along the walkway including total 123 sets hydrants at 50m intervals, 20 sets of independent hydrants inside and outside the main tunnel

8

Fire Fighting Facilities

Total 123 sets of foam fire fighting equipment and fire extinguishers equipped in the fire fighting niches

9

Irrigation Pipe

145m long pipe with 5 sprinkler faucet for North portal

120m long pipe with 4 sprinkler faucet for South portal

Ventilation Adit Building:

(1) Ventilation Adit Building
This building locating Air Supply and Exhaust Ventilation System is connected to Ventilation adit for supply and exhaust air to and from the main tunnel. Total floor area is 1,246.8m2, Electric room area consisting of 7 rooms is 145.2m2, Mechanical room for Supply/Exhaust fan is 639.0m2 and Air duct for connecting Ventilation adit is 462.6m2. Height of the rooftop is 12.8m and height of the chimney is 25.8m
(2) Ventilation Adit Connection

Ventilation Adit Facilities include building of electric rooms, airconditioning, ventilation, Duct and nozzle, Air outlet barrier, Corner vane, Mesh fence, Lighting and etc…

Tunnel Ventilation System:

(1) Electrostatic Precipitator System

3 x EP System of air volume 260m3/s and soot collecting efficiency 80~87% complete with 2 x 220kW EP fan for each station, auxiliary machines, high voltage generators, control systems and building of EP chambers including air conditioning, lighting and etc…

(2) Jet Fan System

23 x Jet fans with impeller of 1520mm in diameter and capacity of average air velocity 30.2m/s, 23 x Jet fan switching panel, 12 x Jet fan local switch box, power cables and ground cables to be installed in the walkway of the main tunnel and etc…

 (3) Air Supply and Exhaust Ventilation System

2 x 420kW Supply fan with air volume 140m3/s, 2 x 330kW Exhaust fan with air volume 140m3/s, 4 x Damper, Air ducts, Air nozzle, Corner vane, Operation air supply equipment, 10t and 5t Overhead traveling crane, 4 x Power supply panel, 2 x Local control panel and etc…

Construction Supervision

Top


This homepage is presented by the Consultant Team

Any further question should be forwarded to Webmaster or Consultant Team

 

 


Progress To Date

By Figure
By Primavera



Tunnel Excavation
Record

By Number
By Figure
By Plan
By Chart




Monthly Progress

Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII



News and Events
Project
Public Media
Visitor List



Organization Charts

The Employer
The Consultant
The Contractors
Others



Consultant Office

List of Staff
Members Only



Project Information
Introduction
(MS-PowerPoint)
Project Map
Background
Major Features
Chronicle
Contract Packages
Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII
Natural Conditions
Socio-Economic Dev.



Public Relations
Site Map
Contact Us
Related Agencies
Link
FAQs
Knowledgebase
Guest Book



Our Gallery
Computer Graphics
Perspective
Vietnam
Introduction
Photo Selection



Around Project
Highway Network in
Vietnam
Large-scaledHighway
Projects in Central
of Vietnam



Tiếng Việt



Coordination