Progress Report > Package VII - Infrastructure Development in the
Resettlement Area
Physical Progress | Photographs | Construction Supervision
As of April 30, 2002
Physical Progress
Contractor Construction Company No.185 Commencement of the Works 1st August 2001 Time Elapsed (days) 100 % (2 months extension proposed) Progress Completed 100%. Hand Over on April 29, 2002
Contractor
Construction Company No.185
Commencement of the Works
1st August 2001
100 % (2 months extension proposed)
Photographs
Top
Construction Supervision
In this month the Contractor is carrying out continuously of construction activities, major items to be as follows: - Embankment works. - Internal road filling. - Treatment reservoir. - Kindergarten - Drainage system. - Curb and sidewalk slab - Mortar riprap for slope protection of Road No.2.
In this month the Contractor is carrying out continuously of construction activities, major items to be as follows:
- Embankment works.
- Internal road filling. - Treatment reservoir. - Kindergarten - Drainage system. - Curb and sidewalk slab - Mortar riprap for slope protection of Road No.2.
- Internal road filling.
- Treatment reservoir.
- Kindergarten
- Drainage system.
- Curb and sidewalk slab
- Mortar riprap for slope protection of Road No.2.
Previous month
This homepage is presented by the Consultant Team
Any further question should be forwarded to Webmaster or Consultant Team
Progress To Date By Figure By Primavera Tunnel Excavation Record By Number By Figure By Plan By Chart Monthly Progress Package IA Package IB Package IIA Package IIB Package III Package IV Package V Package VI Package VII News and Events Project Public Media Visitor List Organization Charts The Employer The Consultant The Contractors Others Consultant Office List of Staff Members Only Project Information Introduction (MS-PowerPoint) Project Map Background Major Features Chronicle Contract Packages Package IA Package IB Package IIA Package IIB Package III Package IV Package V Package VI Package VII Natural Conditions Socio-Economic Dev. Public Relations Site Map Contact Us Related Agencies Link FAQs Knowledgebase Guest Book Our Gallery Computer Graphics Perspective Vietnam Introduction Photo Selection Around Project Highway Network in Vietnam Large-scaledHighway Projects in Central of Vietnam Tiếng Việt Coordination