As of April 30, 2002

Physical Progress

Contractor

Construction Company No.185

Commencement of the Works

1st August 2001

Time Elapsed (days)

100 % (2 months extension proposed)

Progress Completed 100%. Hand Over on April 29, 2002

 

Photographs

 

Top

Construction Supervision

In this month the Contractor is carrying out continuously of construction activities, major items to be as follows:

- Embankment works.

- Internal road filling.

- Treatment reservoir.

- Kindergarten

- Drainage system.

- Curb and sidewalk slab

- Mortar riprap for slope protection of Road No.2.

Top

Previous month


This homepage is presented by the Consultant Team

Any further question should be forwarded to Webmaster or Consultant Team

 

 


Progress To Date

By Figure
By Primavera



Tunnel Excavation
Record

By Number
By Figure
By Plan
By Chart




Monthly Progress

Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII



News and Events
Project
Public Media
Visitor List



Organization Charts

The Employer
The Consultant
The Contractors
Others



Consultant Office

List of Staff
Members Only



Project Information
Introduction
(MS-PowerPoint)
Project Map
Background
Major Features
Chronicle
Contract Packages
Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII
Natural Conditions
Socio-Economic Dev.



Public Relations
Site Map
Contact Us
Related Agencies
Link
FAQs
Knowledgebase
Guest Book



Our Gallery
Computer Graphics
Perspective
Vietnam
Introduction
Photo Selection



Around Project
Highway Network in
Vietnam
Large-scaledHighway
Projects in Central
of Vietnam



Tiếng Việt



Coordination