As of March 31, 2005

Physical Progress

Contractor

JV of Dong Ah and Song Da

Commencement of the Works

1st October 2000

Contract Period

1460 days (Until September 30, 2004)

Time Elapsed (days)

1588 of 1460 (108.77%)

Progress

 

Main Tunnel(2417m)

Excavated 2379m in total (100%)

Evacuation Tunnel(2429m)

Excavated 2411m in total (100%)

Access Road to Water Reservoir.

Completed

Bridge No.1(58m)

Completed

Issuance of Taking Over Certificate

25 January 2005

Site Handover to HAMADECO

31 March 2005

Additional Scope of Works

Completed

- Landscaping of South Portal Plaza

- Protection Wall for Down Pipe

Ongoing

-  Reinforcement of Submergible Section

- Project Monument

Photographs

Top

Construction Supervision

Summary from Contractor

Main Tunnel and Evacuation Tunnel excavation was completely finished. Bench excavation and tunnel lining were completed. The rear concrete works is ongoing.

Construction Supervision by Engineer

Cut and Cover Section

Construction of asphalt concrete     (6cm)                                     11000m2

Main Tunnel Rear Work

Finished

Road work

Profile line marking at roadway was completed                           2423m

Rubber guard cone was completed                                             95 pieces

Stainless steel revision shaft cover         was completed                  96 pieces

Evacuation Tunnel Rear Work

Construction of penetration layer was completed                  875m

Construction of concrete pavement was completed                  60m            

Major Events and Issues

Previous month


This homepage is presented by the Consultant Team

Any further question should be forwarded to Webmaster or Consultant Team

 

 


Progress To Date

By Figure
By Primavera



Tunnel Excavation
Record

By Number
By Figure
By Plan
By Chart




Monthly Progress

Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII



News and Events
Project
Public Media
Visitor List



Organization Charts

The Employer
The Consultant
The Contractors
Others



Consultant Office

List of Staff
Members Only



Project Information
Introduction
(MS-PowerPoint)
Project Map
Background
Major Features
Chronicle
Contract Packages
Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII
Natural Conditions
Socio-Economic Dev.



Public Relations
Site Map
Contact Us
Related Agencies
Link
FAQs
Knowledgebase
Guest Book



Our Gallery
Computer Graphics
Perspective
Vietnam
Introduction
Photo Selection



Around Project
Highway Network in
Vietnam
Large-scaledHighway
Projects in Central
of Vietnam



Tiếng Việt



Coordination