Contractor
|
Matsushita
- Itochu Consortium
|
Commencement
of the Works
|
13
March 2002
|
Contract
period |
1080
days (Until March 12, 2005) |
Time
Elapsed (days) |
868
of 1080 (80.37%) Remaining 212 days |
Progress
|
|
|
-
Continue the construction of EP stations.
-
Concrete placed for columns, beams, slab and wall.
|
Photographs
 |
Piping
for Water Supply System at South Portal Plaza
|
 |
Weight
Measuring for ALC Boards
|
 |
ALC
Boads Installation at EP1
|
 |
ALC
Boards Installation at EP1
|
 |
Installed
ALC Boards at EP1
|
 |
Installing
Brackets for Ceiling at EP2
|
 |
Ep
Fan Pedestal at EP1
|
 |
Air
Outlet Side Wall at EP3
|
 |
ALC
Boards Installed at EP3
|
 |
EP
Fan Pedestal at EP3
|
 |
Support
& Hunger for Airconditioner at SS5
|
 |
Inspection
for Steel Bar Arrangement at Ventilation Adit Building
|
 |
Fixed
Point View of Ventilation Adit Building on July 29, 2004
|
 |
Devanning
of EP Fan at Warehouse
|
Summary
Water
Supply and Treatment System:
Reinforcing
steel bars for High Level Reservoir installed.
Continue
the Hydrant piping installation in the main tunnel.
Tunnel
Ventilation System:
Pedestal
for EP and steel structure for separation wall at EP1 and EP3.
Anchoring
work for EP2 finished.
EP
and auxiliary machines for EP1, 2 and 3, EP fan for EP1 and 3,
Supply/Exhaust fans, EP control equipment are imported and stored at
warehouse in Danang.
Ventilation
Adit Building
Concrete
placed for columns, beams, slabs and wall.
Construction
Supervision
Permanent
work
High
Level Reservoir:
Reinforcing
bar and forming work for wall, Structure concrete work for wall
Installation
of water pipes in the main tunnel
Marking
Finished
Anchoring
Finished
Pressure
test Zone K, J2
(Jul 01 ~ Jul 07), Zone G (Jul 06 ~ Jul 14),
Zone
H (Jul 17 ~ Jul 24), Zone I,J1 (Jul 09 ~ Jul 16)
South
Portal Plaza
Excavation
work 280 m3
Piping
work 110 m
Backfilling
work 430 m3
Ventilation
System
<EP1,
EP3>
-
Ceiling work and Installation of ALC
-
Installation for inside wall of EP room
-
Installation of EP Fan pedestal
<EP2>
-
Starting ceiling work
-
Installation of crane for EP and EP Fan
Ventilation
Adit Building: Continuing
Concrete
placing and bar arrangement for beams and columns
Ventilation
Adit Connection:
Starting
ceiling work
Top
|