Welcome to Our Site!
 

As of July 31, 2004

Physical Progress

Contractor

Matsushita - Itochu Consortium

Commencement of the Works

13 March 2002

Contract period 1080 days (Until March 12, 2005)
Time Elapsed (days) 868 of 1080 (80.37%) Remaining 212 days

Progress

 

- Continue the construction of EP stations.

- Concrete placed for columns, beams, slab and wall.

Photographs

Piping for Water Supply System at South Portal Plaza
Weight Measuring for ALC Boards
ALC Boads Installation at EP1
ALC Boards Installation at EP1
Installed ALC Boards at EP1
Installing Brackets for Ceiling at EP2
Ep Fan Pedestal at EP1
Air Outlet Side Wall at EP3
ALC Boards Installed at EP3
EP Fan Pedestal at EP3
Support & Hunger for Airconditioner at SS5
Inspection for Steel Bar Arrangement at Ventilation Adit Building
Fixed Point View of Ventilation Adit Building on July 29, 2004
Devanning of EP Fan at Warehouse

Top

Construction Supervision

Summary

Water Supply and Treatment System:

Reinforcing steel bars for High Level Reservoir installed.

Continue the Hydrant piping installation in the main tunnel.

Tunnel Ventilation System:

Pedestal for EP and steel structure for separation wall at EP1 and EP3.

Anchoring work for EP2 finished.

EP and auxiliary machines for EP1, 2 and 3, EP fan for EP1 and 3, Supply/Exhaust fans, EP control equipment are imported and stored at warehouse in Danang.

Ventilation Adit Building

Concrete placed for columns, beams, slabs and wall.

Construction Supervision

Permanent work

High Level Reservoir: 

Reinforcing bar and forming work for wall, Structure concrete work for wall

Installation of water pipes in the main tunnel

Marking          Finished

Anchoring          Finished

Pressure test          Zone K, J2 (Jul 01 ~ Jul 07), Zone G (Jul 06 ~ Jul 14),

Zone H (Jul 17 ~ Jul 24), Zone I,J1 (Jul 09 ~ Jul 16)

South Portal Plaza

Excavation work          280 m3

Piping work          110 m

Backfilling work         430 m3

Ventilation System

<EP1, EP3>

- Ceiling work and Installation of ALC

- Installation for inside wall of EP room

- Installation of EP Fan pedestal

<EP2>

- Starting ceiling work

- Installation of crane for EP and EP Fan

Ventilation Adit Building: Continuing 

Concrete placing and bar arrangement for beams and columns

Ventilation Adit Connection: 

Starting ceiling work

Top

Previous month / Next month


This homepage is presented by the Consultant Team

Any further question should be forwarded to Webmaster or Consultant Team

 

 


Progress To Date

By Figure
By Primavera



Tunnel Excavation
Record

By Number
By Figure
By Plan
By Chart




Monthly Progress

Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII



News and Events
Project
Public Media
Visitor List



Organization Charts

The Employer
The Consultant
The Contractors
Others



Consultant Office

List of Staff
Members Only



Project Information
Introduction
(MS-PowerPoint)
Project Map
Background
Major Features
Chronicle
Contract Packages
Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII
Natural Conditions
Socio-Economic Dev.



Public Relations
Site Map
Contact Us
Related Agencies
Link
FAQs
Knowledgebase
Guest Book



Our Gallery
Computer Graphics
Perspective
Vietnam
Introduction
Photo Selection



Around Project
Highway Network in
Vietnam
Large-scaledHighway
Projects in Central
of Vietnam



Tiếng Việt



Coordination