Contractor
|
Matsushita
- Itochu Consortium
|
Commencement
of the Works
|
13
March 2002
|
Contract
period |
1080
days (Until March 12, 2005) |
Time
Elapsed (days) |
838
of 1080 (77.59%) Remaining 242 days |
Progress
|
|
|
-
Continue the installation of water pipes in the main
tunnel.
-
Install the pedestrian for EP and steel structure for
separation wall and complete the anchoring &
fabrication of jet fans. |
Summary
Water
Supply and Treatment System:
Reinforcing
steel bars for High Level Reservoir installed.
Continue
the Hydrant piping installation in the main tunnel.
Tunnel
Ventilation System:
Pedestal
for EP and steel structure for separation wall at EP1 and EP3.
Anchoring
work for EP2 finished.
EP
and auxiliary machines for EP1, 2 and 3, EP fan for EP1 and 3,
Supply/Exhaust fans, EP control equipment are imported and stored at
warehouse in Danang.
Ventilation
Adit Building
Concrete
placed for columns, beams, slabs and wall.
Construction
Supervision
Permanent
work
High
Level Reservoir:
Reinforcing
bar and forming work for wall, Structure concrete work for wall
Installation
of water pipes in the main tunnel
Marking
Finished
Anchoring
Finished
Pressure
test Zone K, J2
(Jul 01 ~ Jul 07), Zone G (Jul 06 ~ Jul 14),
Zone
H (Jul 17 ~ Jul 24), Zone I,J1 (Jul 09 ~ Jul 16)
South
Portal Plaza
Excavation
work 280 m3
Piping
work 110 m
Backfilling
work 430 m3
Ventilation
System
<EP1,
EP3>
-
Ceiling work and Installation of ALC
-
Installation for inside wall of EP room
-
Installation of EP Fan pedestal
<EP2>
-
Starting ceiling work
-
Installation of crane for EP and EP Fan
Ventilation
Adit Building:Continuing
Concrete
placing and bar arrangement for beams and columns
Ventilation
Adit Connection:
Starting
ceiling work
Top
|