As of May 31, 2004

Physical Progress

Contractor

Matsushita - Itochu Consortium

Commencement of the Works

13 March 2002

Contract period 1080 days (Until March 12, 2005)
Time Elapsed (days) 808 of 1080 (74.81%) Remaining 272 days

Progress

 
 

- Continue the work for Water Supply and Treatment System and Tunnel Ventilation.

Photographs

Bell Mouth Installed for EP1
Bell Mouth Installed for EP3
Parts of EP Fan Pedestal
Bell Mouth of EP1 View From Inlet Side
Manufacturing of Guide Vane at the Factory in Danang
Construction Work for Ventilation Adit Building

Top

Construction Supervision

Summary

Water Supply and Treatment System:

Reinforcing steel bars for High Level Reservoir installed.

Continue the Hydrant piping installation in the main tunnel.

Tunnel Ventilation System:

Shop drawing for machinery of Ventilation System were approved.

Start the Building work of ceiling for EP1 and EP3 and Anchoring work for EP2.

EP and auxiliary machines for EP1, 2 and 3, EP fan for EP1 and 3, Supply/Exhaust fans, EP control equipment  were imported and stored in the warehouse in Danang.

Ventilation Adit Building:

Concrete placed for columns, beams, slabs and wall.

Construction Supervision

 Water Supply and Treatment System

+ Installation of water pipes in the main tunnel

- Marking  615m,  Zone I (May 17~19), Zone J1 (May 20~24)

- Anchoring,  995m, Zone H (May 03~06), Zone I (May 20~22),

                           Zone J1 (May 24~31)

- Piping 0m       

- Pressure test  784m,  Zone N (Apr 21~May 06), Zone M (May 06~18)

Tunnel Ventilation System

+ EP1 & EP3                   - Dismantling form of RC wall and repair work

                                      - Installation of Bell mouths

+ EP2                            - Anchoring for building work, Preparing shop drawings

+ Jet Fan   - Cable supports in walkways installed

Ventilation Adit Building

+ Continuing form work for beams, columns and steel bar arrangement

+ Modification of shop drawings

Ventilation Adit Connection

+ Anchoring for building work

+ Installation of brackets

Top

Previous month / Next month

This homepage is presented by the Consultant Team

Any further question should be forwarded to Webmaster or Consultant Team

 

 


Progress To Date

By Figure
By Primavera



Tunnel Excavation
Record

By Number
By Figure
By Plan
By Chart




Monthly Progress

Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII



News and Events
Project
Public Media
Visitor List



Organization Charts

The Employer
The Consultant
The Contractors
Others



Consultant Office

List of Staff
Members Only



Project Information
Introduction
(MS-PowerPoint)
Project Map
Background
Major Features
Chronicle
Contract Packages
Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII
Natural Conditions
Socio-Economic Dev.



Public Relations
Site Map
Contact Us
Related Agencies
Link
FAQs
Knowledgebase
Guest Book



Our Gallery
Computer Graphics
Perspective
Vietnam
Introduction
Photo Selection



Around Project
Highway Network in
Vietnam
Large-scaledHighway
Projects in Central
of Vietnam



Tiếng Việt



Coordination