Welcome to Our Site!
 

As of April 30, 2004

Physical Progress

Contractor

Matsushita - Itochu Consortium

Commencement of the Works

13 March 2002

Contract period 1080 days (Until March 12, 2005)
Time Elapsed (days) 778 of 1080 (72.04%) Remaining 312 days

Progress

 
 

- Continue the installation for water piping for Water Supply and Treatment System in main tunnel

- Place the based concrete for High Level Reservoir

Photographs

Top

Construction Supervision

Summary

Water Supply and Treatment System:

Reinforcing steel bars for High Level Reservoir installed.

Hydrant piping installation in the main tunnel started.

Tunnel Ventilation System:

Continued the building works of ceiling for EP1 and EP3

Survey and anchoring work for EP2 completed

EP and auxiliary machines for EP1, 2 & 3, EP fan for EP1 and 3, Supply/Exhaust fans, EP control equipment were imported and stored at warehouse in Danang.

Ventilation Adit Building

Continue the concrete placing for walls

Construction Supervision

Permanent work

High Level Reservoir:

Installation of reinforcing bars and forming work for wall

Concrete placing for wall

Installation of water pipes in the main tunnel :

Marking                     Zone I (May 16~20), J1 (May 22~26)

Anchoring                 Zone I (May 22~26), J1 (May 27~31)

Piping  Zone G (May 22~31), K (May 22~31)

Pressure test           Zone N (May 21~30), M (May 6~13)

            Zone L (May 14~20)

South Portal Plaza:

Excavation work       100m3

Piping work              170m

Backfilling work        90m3

EP Stations:

- Ceiling work, Installation of RC wall & Separation wall continued for EP1 and EP3

- Start anchoring work for EP2

Ventilation Adit Building:

- Continue concrete placing for beams, slabs and chimny

- Start construction of main building

Ventilation Adit Connection:

Start anchoring work for supply side

Electrical work:

Start installation of Jet fan cable support in walk ways

Top

Previous month / Next month

This homepage is presented by the Consultant Team

Any further question should be forwarded to Webmaster or Consultant Team

 

 


Progress To Date

By Figure
By Primavera



Tunnel Excavation
Record

By Number
By Figure
By Plan
By Chart




Monthly Progress

Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII



News and Events
Project
Public Media
Visitor List



Organization Charts

The Employer
The Consultant
The Contractors
Others



Consultant Office

List of Staff
Members Only



Project Information
Introduction
(MS-PowerPoint)
Project Map
Background
Major Features
Chronicle
Contract Packages
Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII
Natural Conditions
Socio-Economic Dev.



Public Relations
Site Map
Contact Us
Related Agencies
Link
FAQs
Knowledgebase
Guest Book



Our Gallery
Computer Graphics
Perspective
Vietnam
Introduction
Photo Selection



Around Project
Highway Network in
Vietnam
Large-scaledHighway
Projects in Central
of Vietnam



Tiếng Việt



Coordination