Progress Report > Package IV - Mechanical Works
Summary Water Supply and Treatment System: Install the reinforcing the steel bars and buried pipes, water pipe in the main tunnel and finish the building work of intake reservoir Ventilation Adit Building: Place concrete for columns, beams and walls and install the frame work for ceiling Tunnel Ventilation System: Install EP fan and conection duct for EP1 & 3, finish the assembling of Jet Fan and anchoring, import equipment and install the Console and Measuring Panel at OCC and measuring panel and Interlock Panels at SS5. Construction