Welcome to Our Site!
 

 

Progress Report > Package III - Electrical Works

As of January 31, 2005

Physical Progress

Contractor

JV of ABB, Kinden and Vinaincon

Commencement of the Works

14 February 2003

Contract Period 26 months (Until April 13, 2005)
Time Elapsed (days)  707 of 780 (90.64%) Remaining 73 days

Progress

 

Installation of fire rated (FR) cable, supply cables for CCTV cameras, complete the installation work for area lighting floodlighting towers in NPP and NTP. Conduit was installed in sub-base at NPP and SPP for area lighting circuits.

Photographs

Piping Installation at South Bridge No.1
Lighting Installation at South Bridge
Ceiling Mounted Type Luminaties Installation at STG
Excavation for Cable pit at South Road
Cable Tray and Support Installation at S/S 1
Wiring Devices, Pipe and Box Installation at Toll Booth

Top

Construction Supervision

Summary from Contractor

The Contractor's site construction progress for the month of January slowed down because of shortage of LV cable and equipment. Distribution boards, power distribution, monitoring and control panels, telecommunications panels, traffic control/CCTV panels and other panels for substations did not arrive on site until mid January despite being accepted at FAT by the Engineer in early October.

At the end of December PKIII identified to the Engineer a shortage of LV power and control cables because of deficiencies in their purchasing and scheduling. As a result cabling works between equipment inside substations had not yet started at end of January. This work should have been ongoing since late November. All substation buildings had been handed over to PKIII by late December 2004, starting with availability of S/S#7 & 8 in May and S/S#5 in August 2004.

Installation of road lighting pole foundations along the south road was substantially completed as was the erection of the 9m poles and pole top luminaires. Tunnel overhead works were limited to cable ladder crossings at EP and VAC intersections with main tunnel, installation of brackets for the support of radio rebroadcast (RRB) coaxial antenna, fire sensor cable, and CCTV camera supports. Conduit and boxes continue to be installed in VAB as PKIV work progresses.

Medium voltage (MV) cable pulling began at the end of October in the main tunnel and continued in the ventilation adit and on Lang Co bridge. Approximately 90% of MV cable joints in the main tunnel have been done. The installation of MV cable from S/S#3 to S/S#6 inside the adit cannot be completed because, as with LV cable, the Contractor did not order the correct amount of MV cable and is now seeking additional lengths.

Design work at site continues on the preparation and submittal of installation shop drawings. Detailed design continued in ABB Finland on systems (Fire alarm, and radio rebroadcast (RRB).  Factory acceptance tests (FAT) were completed in early October in Finland on traffic control, lighting control, power distribution control, and main SCADA systems and on systems integration. 

PKIII turned over responsibility for maintenance of all of PKV works (OCC building and power system) to HAMADECO in January but continued to support HAMADECO until end of January.

Construction Supervision

Top

Previous month / Next month


This homepage is presented by the Consultant Team

Any further question should be forwarded to Webmaster or Consultant Team

 

 


Progress To Date

By Figure
By Primavera



Tunnel Excavation
Record

By Number
By Figure
By Plan
By Chart




Monthly Progress

Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII



News and Events
Project
Public Media
Visitor List



Organization Charts

The Employer
The Consultant
The Contractors
Others



Consultant Office

List of Staff
Members Only



Project Information
Introduction
(MS-PowerPoint)
Project Map
Background
Major Features
Chronicle
Contract Packages
Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII
Natural Conditions
Socio-Economic Dev.



Public Relations
Site Map
Contact Us
Related Agencies
Link
FAQs
Knowledgebase
Guest Book



Our Gallery
Computer Graphics
Perspective
Vietnam
Introduction
Photo Selection



Around Project
Highway Network in
Vietnam
Large-scaledHighway
Projects in Central
of Vietnam



Tiếng Việt



Coordination