Progress Report > Package III - Electrical Works

As of June 2004, 2004

Physical Progress

Contractor

JV of ABB, Kinden and Vinaincon

Commencement of the Works

14 February 2003

Contract Period 26 months (Until April 13, 2005)
Time Elapsed (days)  497 of 780 (63.71%) Remaining 283days

Progress

 

- Continue the installation of HDPE conduit supports under the tunnel walkway and southern bridges.

- Carry out the Routine factory tests on medium voltage, low voltage, fire resistant cables, inverters, UPS and battery charger systems.

Photographs


HDPE Installation at South Bridge
HDPE Installation at South Bridge
Pipe Installation at S/S 5
Wiring Device Installation at S/S 5
Manhole Installation at South Toll Plaza
Manhole Installation at South Toll Gate
Excavation for Area Lighting at South Toll Plaza
Re-Bar Work for Area Lighting at South Toll Plaza
Pipe Installation at VAB
Pipe Installation at VAB
Pipe Installation at VMB
Pipe Installation at VMB

Top

Construction Supervision

The Contractor had temporarily stopped the marking (setting out) of tunnel walls because of modification works to installation scaffolding but work has resumed. Overhead anchor bolt, bracket and cable ladder installation in the tunnel began in late June. Installation of HDPE conduit supports under the tunnel walkway and southern bridges continued. Electrical installation work began in Substation No. 5 and on foundations for floodlight towers.

Design work at site has been the preparation and submittal of installation shop drawings. Detailed design continues in ABB Finland on systems (Fire alarm, communications, radio rebroadcast, traffic control, lighting control and main SCADA systems) and systems integration.

PKIII continues to participate in the hand over of sections of walkways and east side duct banks in the tunnel from the civil contractors. The hand over allows PKIII (and PKIV) access to install conduit in the trench under the walkways.

Coordination is still ongoing between PKIII and PKIV.

Routine factory tests were carried out in June on medium voltage, low voltage and fire resistant cables, and on inverters, UPS and battery charger systems. The Contractor is beginning to receive equipment delivery from Europe including 22kV GIS switchboards and distribution transformers.

The Engineer identified the North and South portal plaza areas as critical civil construction areas to enable early installation of main electrical cables and early supply of power for ventilation fan testing. The civil contractors began work in early March (PK1B) and late March (PK1A) in those areas.

PKIII took over maintenance of PKV works as provided for under their contract in May and have now sub-contracted this work to HAMADECO.

Top

Previous month / Next month


This homepage is presented by the Consultant Team

Any further question should be forwarded to Webmaster or Consultant Team

 

 


Progress To Date

By Figure
By Primavera



Tunnel Excavation
Record

By Number
By Figure
By Plan
By Chart




Monthly Progress

Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII



News and Events
Project
Public Media
Visitor List



Organization Charts

The Employer
The Consultant
The Contractors
Others



Consultant Office

List of Staff
Members Only



Project Information
Introduction
(MS-PowerPoint)
Project Map
Background
Major Features
Chronicle
Contract Packages
Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII
Natural Conditions
Socio-Economic Dev.



Public Relations
Site Map
Contact Us
Related Agencies
Link
FAQs
Knowledgebase
Guest Book



Our Gallery
Computer Graphics
Perspective
Vietnam
Introduction
Photo Selection



Around Project
Highway Network in
Vietnam
Large-scaledHighway
Projects in Central
of Vietnam



Tiếng Việt



Coordination