Progress Report > Package III - Electrical Works

As of May 31, 2004

Physical Progress

Contractor

JV of ABB, Kinden and Vinaincon

Commencement of the Works

14 February 2003

Contract Period 26 months (Until April 13, 2005)
Time Elapsed (days) 467 of 780 (59.87%) Remaining 313days

Progress

 

- Installation of HDPE conduit supports under the tunnel walkway and southern bridges.

- Electrical installation work began in Substation No. 5 and on foundations for floodlight towers.

Photographs

South Bridge Piping and Supporting Work-1
South Bridge Piping and Supporting Work-2
Earthing Work for S/S 5-1
Earthing Work for S/S 5-2
Piping Work for South Toll Gate
Piping Work for South Toll Gate
Earthing Work for Ventilation Building
Box and Piping Work for Ventilation Building

Top

Construction Supervision

The Contractor has temporarily stopped the marking (setting out) of tunnel walls for lighting, fire alarm, radio, and CCTV because of modification works to installation scaffolding, additional scaffolding construction, and operation of paving machines by civil contractors. Installation of HDPE conduit supports under the tunnel walkway and southern bridges continues. There are some deficiencies in these installations and are being addressed by Contractor. Electrical installation work began in Substation No. 5 and on foundations for floodlight towers.

Design work at site has been the preparation and submittal of installation shop drawings. Detailed design continues in ABB Finland on systems (Fire alarm, communications, radio rebroadcast, traffic control, lighting control and main SCADA systems) and systems integration.

PKIII continues to participate in the hand over of sections of walkways and east side duct banks in the tunnel from the civil contractors. The hand over allows PKIII (and PKIV) access to install conduit in the trench under the walkways.

Coordination is still ongoing between PKIII and PKIV.

Routine factory tests were carried out in May on fibre optic and medium voltage, low voltage and fire resistant cables. The Contractor is beginning to receive equipment delivery from Europe including 22kV GIS switchboards and distribution transformers.

The Engineer identified the North and South portal plaza areas as critical civil construction areas to enable early installation of main electrical cables and early supply of power for ventilation fan testing. The civil contractors began work in early March (PK1B) and late March (PK1A) in those areas.

Top

Previous month / Next month


This homepage is presented by the Consultant Team

Any further question should be forwarded to Webmaster or Consultant Team

 

 


Progress To Date

By Figure
By Primavera



Tunnel Excavation
Record

By Number
By Figure
By Plan
By Chart




Monthly Progress

Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII



News and Events
Project
Public Media
Visitor List



Organization Charts

The Employer
The Consultant
The Contractors
Others



Consultant Office

List of Staff
Members Only



Project Information
Introduction
(MS-PowerPoint)
Project Map
Background
Major Features
Chronicle
Contract Packages
Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII
Natural Conditions
Socio-Economic Dev.



Public Relations
Site Map
Contact Us
Related Agencies
Link
FAQs
Knowledgebase
Guest Book



Our Gallery
Computer Graphics
Perspective
Vietnam
Introduction
Photo Selection



Around Project
Highway Network in
Vietnam
Large-scaledHighway
Projects in Central
of Vietnam



Tiếng Việt



Coordination