Progress Report > Package III - Electrical Works
Photographs
The
Contractor has temporarily stopped the marking (setting out) of
tunnel walls for lighting, fire alarm, radio, and CCTV because
of modification works to installation scaffolding, additional
scaffolding construction, and operation of paving machines by
civil contractors. Installation of HDPE conduit supports under
the tunnel walkway and southern bridges continues. There are
some deficiencies in these installations and are being addressed
by Contractor. Electrical installation work began in Substation
No. 5 and on foundations for floodlight towers. Design
work at site has been the preparation and submittal of
installation shop drawings. Detailed design continues in ABB
Finland on systems (Fire alarm, communications, radio
rebroadcast, traffic control, lighting control and main SCADA
systems) and systems integration. PKIII
continues to participate in the hand over of sections of
walkways and east side duct banks in the tunnel from the civil
contractors. The hand over allows PKIII (and PKIV) access to
install conduit in the trench under the walkways. Coordination
is still ongoing between PKIII and PKIV. Routine
factory tests were carried out in May on fibre optic and medium
voltage, low voltage and fire resistant cables. The Contractor
is beginning to receive equipment delivery from Europe including
22kV GIS switchboards and distribution transformers. The Engineer identified the North and South portal plaza areas as critical civil construction areas to enable early installation of main electrical cables and early supply of power for ventilation fan testing. The civil contractors began work in early March (PK1B) and late March (PK1A) in those areas. This homepage is presented by the Consultant Team Any further question should be forwarded to Webmaster or Consultant Team
|
|
||||||||||||||||||||||||||||||