Welcome to Our Site!
 

 

Progress Report > Package III - Electrical Works

As of July 31, 2004

Physical Progress

Contractor

JV of ABB, Kinden and Vinaincon

Commencement of the Works

14 February 2003

Contract Period 26 months (Until April 13, 2005)
Time Elapsed (days) 527 of 780 (67.56%) Remaining 253days

Progress

 

- Started the electrical installation work for SS5.

- Continue the detailed design for Fire alarm, cummunications, radio rebroadcast, traffic control and main SCADA systems.

 

Photographs

Installation of Cable Ladder And Luminaries In Tunnel
Area Lighting Survey and Excavation Work for NPP
Area Lighting Foundation Work for SPP
Lightning System for VMB

Top

Construction Supervision

The Contractor's major work remains the installation of cable ladder and luminaries supports, cable ladder, and luminaries in the main tunnel. Additional works include general lighting and small power conduits in Sub station #5 and conduit installations on the underside of south road bridges. Electrical installation work began in Substation No. 5 and continued on foundations for 25 metre high floodlight towers in front of north and south portals.

Design work at site has been the preparation and submittal of installation shop drawings. Detailed design continues in ABB Finland on systems (Fire alarm, communications, radio rebroadcast, traffic control, lighting control and main SCADA systems) and systems integration.

PKIII continued to participate in the hand over of sections of walkways and east side duct banks in the tunnel from the civil contractors. The hand over allows PKIII (and PKIV) access to install conduit in the trench under the walkways and for PKIII to pull cables from OCC to S/S#5 along the east side duct bank.

Coordination is still ongoing between PKIII and PKIV.

Routine factory tests were carried out in June on medium voltage, low voltage and fire resistant cables, and on inverters, UPS and battery charger systems. The Contractor is beginning to receive equipment delivery from Europe including 22kV GIS switchboards and distribution transformers in June.

The Engineer identified the North and South portal plaza areas as critical civil construction areas to enable early installation of main electrical cables and early supply of power for ventilation fan testing. The south portal area duct banks were handed over in early July for PKIII installation of cable supports and to begin cable pulling in August. The north portal area duct banks were handed over on the 5th. August.

PKIII took over maintenance of PKV works as provided for under their contract in May and were to negotiate to sub-contracted this work to HAMADECO. However HAMADECO declined to sign PKIII sub-contract agreement citing unacceptable insurance clauses.  These clauses were copied from PKIII contract documents. PKIII will continue with maintenance of PKV works without sub-contract.

Top

Previous month / Next month


This homepage is presented by the Consultant Team

Any further question should be forwarded to Webmaster or Consultant Team

 

 


Progress To Date

By Figure
By Primavera



Tunnel Excavation
Record

By Number
By Figure
By Plan
By Chart




Monthly Progress

Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII



News and Events
Project
Public Media
Visitor List



Organization Charts

The Employer
The Consultant
The Contractors
Others



Consultant Office

List of Staff
Members Only



Project Information
Introduction
(MS-PowerPoint)
Project Map
Background
Major Features
Chronicle
Contract Packages
Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII
Natural Conditions
Socio-Economic Dev.



Public Relations
Site Map
Contact Us
Related Agencies
Link
FAQs
Knowledgebase
Guest Book



Our Gallery
Computer Graphics
Perspective
Vietnam
Introduction
Photo Selection



Around Project
Highway Network in
Vietnam
Large-scaledHighway
Projects in Central
of Vietnam



Tiếng Việt



Coordination