Progress Report > Package IIB - Southern HighwaySection
Construction Supervision Summary from Contractor The whole 6 bridges on the route was completed in construction work. At present, the last works were expansion joint, painting work of handrail and install the related facilities on the bridges. Construction Supervision by Engineer Quantity summary of some main items
Estimation for the work progress and quality: Until now the main work of road work of Package 2B (Pavement work) has been completed. Checking quality has been carried out. The Contractor is carrying out the last works (Side ditch, Traffic safety system v.v…). The excavation work has been completed, however the finished work is still not good. The Engineer has requested the contractor to repair the slope surface. For the asphalt concrete, generally quality can be accepted. Concrete works is can be accepted, however the esthetic quality is not good enough. Bridge work: Whole 6 Bridges on the Route have been completed in construction work. At present, the last works are expansion joint, painting work of handrail and install related facilities on the Bridges. This homepage is presented by the Consultant Team Any further question should be forwarded to Webmaster or Consultant Team
|
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||