As of July 31, 2004

Physical Progress

Contractor

JV of Cienco, Lung Lo and Vinawaco

Commencement of the Works

26 July 2001

Contract period

960 days (Until March 25, 2004)

Time Elapsed (days)

1085 of 960 (113.02%)

Progress

 

The Contractor is carrying out the last works. The Pavement work completed. Checking quality was carried out.

Photographs

Top

Construction Supervision

Summary from Contractor

The whole 6 bridges on the route was completed in construction work. At present, the last works were expansion joint, painting work of handrail and install the related facilities on the bridges.

Construction Supervision by Engineer

Quantity summary of some main items

Item

Quantity

Completed quantity

Percentage of completed quantity

Road Quantity

 

 

 

Excavation (m3)

 

 

100%

Embankment (m3)

 

 

100%

Pavement Quantity:

 

 

 

Subbase (m3)

 

 

100%

Base (m3)

 

 

100%

Binder Course (m2)

42873

42015

100%

Surface Course (m2)

53719

26000

100%

Ditch Quantity

 

 

 

Side Ditch

 

 

80%

Top and Bench Ditch

 

 

100%

Drain culvert Quantity

 

 

100%

Traffic Safety Quantity

(Sign Port, Traffic Sign, Guardrail, Painting)

 

 

0%

Top Soil and Slope Protection

 

 

50%

Toll Plaza building

 

 

100%

Side walk of connection road

10000

3000

30%

 Estimation for the work progress and quality: Until now the main work of road work of Package 2B (Pavement work) was completed. Checking quality was carried out. The Contractor is carrying out the last works (Side ditch, Traffic safety system v.v…). The excavation work has been completed, however the finished work is still not good. The Engineer has requested the contractor to repair the slope surface. For the asphalt concrete, generally quality can be accepted. Concrete works is can be accepted, however the esthetic quality is not good enough.  

Bridge work: Whole 6 Bridges on the Route have been completed in construction work. At present, the last works are expansion joint, painting work of handrail and install related facilities on the Bridges.  

Top

Previous month / Next month


This homepage is presented by the Consultant Team

Any further question should be forwarded to Webmaster or Consultant Team

 

 


Progress To Date

By Figure
By Primavera



Tunnel Excavation
Record

By Number
By Figure
By Plan
By Chart




Monthly Progress

Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII



News and Events
Project
Public Media
Visitor List



Organization Charts

The Employer
The Consultant
The Contractors
Others



Consultant Office

List of Staff
Members Only



Project Information
Introduction
(MS-PowerPoint)
Project Map
Background
Major Features
Chronicle
Contract Packages
Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII
Natural Conditions
Socio-Economic Dev.



Public Relations
Site Map
Contact Us
Related Agencies
Link
FAQs
Knowledgebase
Guest Book



Our Gallery
Computer Graphics
Perspective
Vietnam
Introduction
Photo Selection



Around Project
Highway Network in
Vietnam
Large-scaledHighway
Projects in Central
of Vietnam



Tiếng Việt



Coordination