Progress Report > Package IIB - Southern HighwaySection
Photographs Construction Supervision Summary from Contractor The
whole 6 bridges on the route was completed in construction
work. At present, the last works were expansion
joint, painting work of handrail and install the
related facilities on the bridges. Construction Supervision by Engineer Road work: Quantity summary of some main items
Estimation
for the work progress and quality: Until
now the main work of road work of Package 2B (Pavement
work) has been completed. Checking quality has been
carried out. The Contractor is carrying out the
last works (Side ditch, Traffic safety system v.v…).
The excavation work has been completed, however
the finished work is still not good. The Engineer
has requested the contractor to repair the slope
surface. For the asphalt concrete, generally quality
can be accepted. Concrete works is can be accepted,
however the esthetic quality is not good enough.
Bridge
work: Whole 6 Bridges on the Route have been completed in construction work. At present, the last works are expansion joint, painting work of handrail and install related facilities on the Bridges. This homepage is presented by the Consultant Team Any further question should be forwarded to Webmaster or Consultant Team
|
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||