As of April 30, 2004

Physical Progress

Contractor

JV of Cienco, Lung Lo and Vinawaco

Commencement of the Works

26 July 2001

Contract period

960 days (Until March 25, 2004)

Time Elapsed (days)

995 of 960 (103.65%)

Progress

 

Bridge No.2 (334m)

Substructure, Superstructure, waterproofing membrance work completed: 100%. Asphalt work 30%

Bridge No.3 (033m)

Total completion 100%

Bridge No.4 (175m)

Total completion 100%

Bridge No.5 (133m)

Total completion 100%

Bridge No.6 (150m)

Substructure, Superstructure, waterproofing membrance work completed: 100%. Asphalt work not yet started.

Bridge No.7 (133m)

Substructure, Superstructure, waterproofing membrance work completed: 100%. Asphalt work not yet started.

Photographs

Top

Construction Supervision

Summary from Contractor

Bridge No.2: 

Substructure, superstructure and waterproofing membrance were 100% completed. Asphalt Concrete was 30% completed.

Bridge No.3: 100% completed

Bridge No.4: 100% completed

Bridge No.5: 100% completed

Bridge No.6: Substructure, superstructure and waterproofing membrance were 100% completed. Asphalt Concrete was not yet started.

Bridge No.7: Substructure, superstructure and waterproofing membrance were 100% completed. Asphalt Concrete was not yet started.

Construction Supervision by Engineer

Road work: Quantity summary of some main items

Item

Quantity

Completed quantity

Completion Percentage

Road Quantity

 

 

 

Excavation (m3)

 

 

100%

Embankment (m3)

 

 

100%

Pavement Quantity:

 

 

 

Subbase (m3)

 

 

100%

Base (m3)

 

 

100%

Binder Course (m2)

42873

42015

98%

Surface Course (m2)

53719

26000

48%

Ditch Quantity

 

 

 

Side Ditch

 

 

70%

Top and Bench Ditch

 

 

85%

Drain culvert Quantity

 

 

98%

Traffic Safety Quantity

(Sign Port, Traffic Sign, Guardrail, Painting)

 

 

0%

Top Soil and Slope Protection

 

 

50%

Toll Plaza building

 

 

98%

 

Bridge works: 

Whole 6 Bridges on the Route have been completed in construction work. At present, the last works are expansion joint, painting work of handrail and install related facilities on the Bridges

Item

Quantity

Completed quantity

Completion Percentage

Bridge No.2

 

 

 

Substructure

 

 

100%

Superstructure

 

 

100%

Waterproofing membrane

 

 

100%

Asphalt Concrete

 

 

30%

Bridge No.3

 

 

 

Substructure

 

 

100%

Superstructure

 

 

100%

Waterproofing membrane

 

 

100%

Asphalt Concrete

 

 

100%

Bridge No.4

 

 

 

Substructure

 

 

100%

Superstructure

 

 

100%

Waterproofing membrane

 

 

100%

Asphalt Concrete

 

 

100%

Bridge No.5

 

 

 

Substructure

 

 

100%

Superstructure

 

 

100%

Waterproofing membrane

 

 

100%

Asphalt Concrete

 

 

100%

Bridge No.6

 

 

 

Substructure

 

 

100%

Superstructure

 

 

100%

Waterproofing membrane

 

 

100%

Asphalt Concrete

 

 

00%

Bridge No.7

 

 

 

Substructure

 

 

100%

Superstructure

 

 

100%

Waterproofing membrane

 

 

100%

Asphalt Concrete

 

 

00%

Top

Previous month / Next month


This homepage is presented by the Consultant Team

Any further question should be forwarded to Webmaster or Consultant Team

 

 


Progress To Date

By Figure
By Primavera



Tunnel Excavation
Record

By Number
By Figure
By Plan
By Chart




Monthly Progress

Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII



News and Events
Project
Public Media
Visitor List



Organization Charts

The Employer
The Consultant
The Contractors
Others



Consultant Office

List of Staff
Members Only



Project Information
Introduction
(MS-PowerPoint)
Project Map
Background
Major Features
Chronicle
Contract Packages
Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII
Natural Conditions
Socio-Economic Dev.



Public Relations
Site Map
Contact Us
Related Agencies
Link
FAQs
Knowledgebase
Guest Book



Our Gallery
Computer Graphics
Perspective
Vietnam
Introduction
Photo Selection



Around Project
Highway Network in
Vietnam
Large-scaledHighway
Projects in Central
of Vietnam



Tiếng Việt



Coordination