Progress Report > Package IIB - Southern HighwaySection
Construction Supervision Summary from Contractor Bridge No.2: All sub-structures were completed for concrete work. All spans of launching and 10 spans of deck slab were completed. Total activities completion was 99%. Progress of construction was delayed in comparison with the progress schedule. Bridge No.3: All sub-structures were completed for concrete work. Launching work was finished. Total activities completion was 98%. Progress of construction was delayed in comparison with the progress schedule. Bridge
No.4: All sub-structures were completed for
concrete work. All launching work and deck slabs
were completed and remaining expansion joints. Total
activities completion was 99%. Progress of construction
was delayed in comparision with the progress schedule. Bridge
No.5: All sub-structures were completed for
concrete work. All spans of launching and all spans
of deck slab were completed. Total activities completion
was 98%. Progress of construction was delayed in
comparision with the progress schedule. Bridge No.6: All sub-structures were completed for concrete work. All spans of launching and 4 spans of diaphram were completed. All spans deck slab were completed. Total activities completion was 99%. Construction progress was delayed in comparison with the progress schedule. Bridge No.7: All sub-structures were completed for concrete work. All launching work and all spans of deck slab were completed. Total activities completion was 98%. Progress of construction was delayed in comparison with the progress schedule. Construction Supervision by Engineer Clearing and grubbing: All clearing and grubbing area were completed Earthworks: Excavation work was under construction and 659,000m3 of 659,000m3 was completed. Embankment work was under constructing and 121,218 m3 of 121,218 m3 was completed. Percent completion of excavation 100% and embankment 100%. Pavement: Production of aggregate subbase was at the yard. Subbase work have been finished in this month follows: Top subbase course at Km8+537.605 to Km8+829.975, Km11+560 to Km11+640. Completed aggregate subbase quantity was about 95.20% Base work was completed in this month follows: Base course layer 1 was completed at Km11+560 to Km11+640. Base course layer 2 was completed at Km Km8+863.375 to Km9+347.02, Km9+572.25 to Km9+680.9, Km10+633.17 to Km11+100, Km11+400 to Km11+532.535, and Km0+764.97 to Km1+185.09. Completed aggregate base quantity was about 91.35%. Asphalt concrete binder course have been finished in this month follows: Asphalt concrete binder course spread at Km8+863.375 to Km9+347.02, Km9+572.25 to Km9+680.9, Km9+814.35 to Km10+083, Km10+633.15 to Km11+532.535. Completed asphalt concrete binder course quantity was about 43%. Concrete pavement of Toll pllaza from Km11+532.535 to Km11+638.535, completed about 60%. Retaining: Retaining wall at the back of southern abutment bridge No2 and southern abutment bridge No3 and southern abutment bridge No4 were completed 100%. Culvert work:
This homepage is presented by the Consultant Team Any further question should be forwarded to Webmaster or Consultant Team
|
|
||||||||||||||||||||||||||