As of February 28, 2004

Physical Progress

Contractor

JV of Cienco, Lung Lo and Vinawaco

Commencement of the Works

26 July 2001

Contract period

960 days (Until March 25, 2004)

Time Elapsed (days)

935 of 960 (97%) Remaining 25 days

Progress

 

Bridge No.2 (334m)

Total completion 99%

Bridge No.3 (033m)

Total completion 98%

Bridge No.4 (175m)

Total completion 99%

Bridge No.5 (133m)

Total completion 98%

Bridge No.6 (150m)

Total completion 99%

Bridge No.7 (133m)

Total completion 98%

Photographs

Overview of Bridge No.2 from Abutment A2
Road Behind Bridge No.7
Road from Km 11+260 to Km 11+660
Road from Bridge No.3 to Bridge No.4
Road from Bridge No.5 to Bridge No.6
Road from Km 11+660 to Km 11+840
Road at the end point of the Project (Km 12+047)
South Tollgate after Removing scaffold System and Formworks

Top

Construction Supervision

Summary from Contractor

Bridge No.2: All sub-structures were completed for concrete work. All spans of launching and 10 spans of deck slab were completed. Total activities completion was 99%. Progress of construction was delayed in comparison with the progress schedule.

Bridge No.3: All sub-structures were completed for concrete work. Launching work was finished. Total activities completion was 98%. Progress of construction was delayed in comparison with the progress schedule.

Bridge No.4: All sub-structures were completed for concrete work. All launching work and deck slabs were completed and remaining expansion joints. Total activities completion was 99%. Progress of construction was delayed in comparision with the progress schedule

Bridge No.5: All sub-structures were completed for concrete work. All spans of launching and all spans of deck slab were completed. Total activities completion was 98%. Progress of construction was delayed in comparision with the progress schedule.

Bridge No.6: All sub-structures were completed for concrete work. All spans of  launching and 4 spans of diaphram were completed. All spans deck slab were completed. Total activities completion was 99%. Construction progress was delayed in comparison with the progress schedule.

Bridge No.7: All sub-structures were completed for concrete work. All launching work and all spans of deck slab were completed. Total activities completion was 98%. Progress of construction was delayed in comparison with the progress schedule.

Construction Supervision by Engineer

Clearing and grubbing: 

All clearing and grubbing area were completed

Earthworks: 

Excavation work was under construction and 657,930 m3 of 659,000m3 was completed. Embankment work was under constructing and 121,218 m3 of 121,218 m3 was completed. Percent completion of excavation 99.8% and embankment 100%. Generally, excavation work was late. The Contractor should be speed-up of work progress.

Pavement: 

Production of aggregate subbase and aggregate base are being at yard.

Subbase work have been finished in this month follows:

Subbase course layer 1 have been finished at Km8+725 to Km8+830, Km9+814 to Km9+830. Subbase course layers 2 have been finished at Km8+537 to Km8+830, Km9+814 to Km9+830, Km10+233 to Km10+500, Km10+633 to Km11+00. Top subbase course at Km8+863 to Km9+374, Km10+233 to Km10+500, Km10+800 to Km11+00. Completed aggregate subbase quantity is about 89.00%.

Base work have been finished in this month follows:

Base course layer 1 have been finished at Km8+863 to Km9+347, Km9+572 to Km9+680, Km9+814 to Km10+083, Km10+233 to Km10+500, Km10+633 to Km11+040, Km11+240 to Km11+560. Base course layer 2 have been finished at Km9+814 to Km10+083, Km10+233 to Km10+500, Km10+633 to Km11+560. Completed aggregate base quantity is about 47%. Asphalt concrete binder course have been finished at 10+250 to Km10+480, Km11+00 to Km11+400. Completed asphalt concrete binder course quantity is about 10%.

Retaining:

Retaining wall at the back of southern abutment bridge No2 and southern abutment bridge No3 and southern abutment bridge No4 have completed 100%

Culvert work:

1. Box culvert at KM9+115 concrete work has completed. 

2. Under pass at KM11+260 have been completed.

3. Pipe culvert at KM11+050 have been completed.

4. Pipe culvert at KM11+290 have been completed.

5. Pipe culvert at KM11+660 is carried out, completed about 20%.

Top

Previous month / Next month


This homepage is presented by the Consultant Team

Any further question should be forwarded to Webmaster or Consultant Team

 

 


Progress To Date

By Figure
By Primavera



Tunnel Excavation
Record

By Number
By Figure
By Plan
By Chart




Monthly Progress

Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII



News and Events
Project
Public Media
Visitor List



Organization Charts

The Employer
The Consultant
The Contractors
Others



Consultant Office

List of Staff
Members Only



Project Information
Introduction
(MS-PowerPoint)
Project Map
Background
Major Features
Chronicle
Contract Packages
Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII
Natural Conditions
Socio-Economic Dev.



Public Relations
Site Map
Contact Us
Related Agencies
Link
FAQs
Knowledgebase
Guest Book



Our Gallery
Computer Graphics
Perspective
Vietnam
Introduction
Photo Selection



Around Project
Highway Network in
Vietnam
Large-scaledHighway
Projects in Central
of Vietnam



Tiếng Việt



Coordination