As of January 31, 2004

Physical Progress

Contractor

JV of Cienco, Lung Lo and Vinawaco

Commencement of the Works

26 July 2001

Contract period

960 days (Until March 25, 2004)

Time Elapsed (days)

905 of 960 (94.27%) Remaining 55 days

Progress

 

Bridge No.2 (334m)

Total completion 97%

Bridge No.3 (033m)

Total completion 97%

Bridge No.4 (175m)

Total completion 98%

Bridge No.5 (133m)

Total completion 97%

Bridge No.6 (150m)

Total completion 97%

Bridge No.7 (133m)

Total completion 97%

Temporary Work

Under construction

Photographs

Overview of Bridge No.2
Deck Slab of Bridge No.2
Bridge No.3
Overview of Bridge No.5
Bridge No.6 from Abutment A1
Overview of Bridge No.7
Road Section From No.3 to Bridge No.4
Road Section from Km.11+660 to Km. 11+260
Toll Gate of South Toll Plaza
South Toll Plaza Building

Top

Construction Supervision

Summary from Contractor

Bridge No.2: All sub-structures were completed for concrete work. All spans of launching and 10 spans of deck slab were completed. Total activities completion was 97%. Progress of construction was delayed in comparison with the progress schedule.

Bridge No.3: All sub-structures were completed for concrete work. Launching work was finished. Diaphragm work and deck slab were finished. Total activities completion was 97%. Total progress was 60 days behind from the expected finishing date by the end of December 2003.

Bridge No.4: All sub-structures were completed for concrete work. All launching work and deck slabs were completed and remaining expansion joints. Total activities completion was 98%. Progress of construction was delayed in comparision with the progress schedule.

Bridge No.5: All sub-structures were completed for concrete work. All spans of launching and all spans of deck slab were completed. Total activities completion was 97%. Progress of construction was delayed in comparison with the progress schedule.

Bridge No.6: All sub-structures were completed for concrete work. All spans of  launching and 4 spans of diaphragm were completed. All spans deck slab were completed. Total activities completion was 97%. Construction progress was delayed in comparison with the progress schedule.

Bridge No.7: All sub-structures were completed for concrete work. All launching work and all spans of deck slab were completed. Total activities completion was 97%. Progress of construction was delayed in comparison with the progress schedule.

Construction Supervision by Engineer

Clearing and grubbing: All clearing and grubbing area were completed

Earthworks: 

Excavation work was under construction and 657,160 m3 of 659,000m3 was completed. Embankment work  was under construction and 121,218 m3 of 121,218 m3 was completed. Percent completion of excavation 99.7% and embankment 100%. Generally, excavation work was late. The Contractor should speed-up the work progress.

Pavement: 

Production of aggregate subbase and aggregate base were at yard. Subbase work was finished in this month: Subbase course layer 1 were finished at Km10+233 to Km10+350, Km10+350 to Km10+499, Km10+633 to Km10+800, Km11+660 to Km11+740. Subbase course layers 2 were finished at Km8+125 to Km8+204, Km10+633 to Km10+800. Top subbase course at Km9+572 to Km9+681, Km9+830 to Km10+083, Km10+633 to Km10+800. Completed aggregate subbase quantity was about 80.00%.

Base work were finished in this month: Base course layer 1 were finished at Km11+040 to Km11+240. Completed aggregate base quantity was about 3%.

Retainning:

Retaining wall at the back of southern abutment bridge No.3 and southern abutment bridge No.4 was completed 100%. Retaining wall at the back of southern abutment bridge No2 was carried out.

Culvert work:

1. Box culvert at KM9+115 concrete work has completed. 

2. Under pass at KM11+260 have been completed.

3. Pipe culvert at KM11+050 have been completed.

4. Pipe culvert at KM11+290 have been completed.

5. Pipe culvert at KM11+660 is carried out.

Schedule overview

Total schedule is just on the schedule based on the new construction schedule establish at November 2003.

Earthwork of road works is also going to be delay. Contractor was requested to review equipment schedule.

Earthwork area 7, area 10 seem to be delayed compared with the expected schedule finishing.

Top

Previous month / Next month


This homepage is presented by the Consultant Team

Any further question should be forwarded to Webmaster or Consultant Team

 

 


Progress To Date

By Figure
By Primavera



Tunnel Excavation
Record

By Number
By Figure
By Plan
By Chart




Monthly Progress

Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII



News and Events
Project
Public Media
Visitor List



Organization Charts

The Employer
The Consultant
The Contractors
Others



Consultant Office

List of Staff
Members Only



Project Information
Introduction
(MS-PowerPoint)
Project Map
Background
Major Features
Chronicle
Contract Packages
Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII
Natural Conditions
Socio-Economic Dev.



Public Relations
Site Map
Contact Us
Related Agencies
Link
FAQs
Knowledgebase
Guest Book



Our Gallery
Computer Graphics
Perspective
Vietnam
Introduction
Photo Selection



Around Project
Highway Network in
Vietnam
Large-scaledHighway
Projects in Central
of Vietnam



Tiếng Việt



Coordination