As of December 31, 2003

Physical Progress

Contractor

JV of Cienco, Lung Lo and Vinawaco

Commencement of the Works

26 July 2001

Contract period

960 days (Until March 25, 2004)

Time Elapsed (days)

875 of 960 (91.14%) Remaining 85 days

Progress

 

Bridge No.2 (334m)

Total completion 97%

Bridge No.3 (033m)

Total completion 90%

Bridge No.4 (175m)

Total completion 98%

Bridge No.5 (133m)

Total completion 97%

Bridge No.6 (150m)

Total completion 95%

Bridge No.7 (133m)

Total completion 97%

Temporary Work

Under construction

Photographs

Top

Construction Supervision

Summary from Contractor

Bridge No.2: All sub-structures were completed for concrete work. All spans of launching and 10 spans of deck slab were completed. Total activities completion was 97%. Progress of construction will be finished at 14th January 2004.

Bridge No.3: All sub-structures were completed for concrete work. Launching work was finished. Diaphragm work and deck slab were finished. Total activities completion was 90%. Total progress was 30 days behind from the expected finishing date by the end of December 2003.

Bridge No.4: All sub-structures were completed for concrete work. All launching work and deck slabs were completed and remaining expansion joints. Total activities completion was 98%. Progress of construction was delayed in comparision with the expected finishing date in the end of December 2003.

Bridge No.5: All sub-structures were completed for concrete work. All spans of launching and all spans of deck slab were completed. Total activities completion was 97%. Progress of construction was delayed in comparision with the expected finishing date in the end of December 2003.

Bridge No.6: All sub-structures were completed for concrete work. All spans of launching and 4 spans of diaphram were completed. 3 spans deck slap were completed. Total activities completion was 95%. Progress of construction will be finished at 30th January 2004.

Bridge No.7: All sub-structures were completed for concrete work. All launching work and all spans of deck slap were completed. Total activities completion was 97%. Progress of construction will be finished at 23nd January 2004.

Construction Supervision by Engineer

Bridge No.2

Substructure

North abutment was completed of concrete works. Pier No.1, 2, 3, 4, 5, 6, 7, 8, 9 were completed of concrete works up to cross head. South abutment was completed of concrete works.

Superstructure

Span 1, 2, 3, 4, 5, 6, 7, 8, 9, 10 were finished the concrete work.

Girder Production

50 nos. of 50 girder was finished production.

Bridge No.3

Substructure:

North Abutment, South Abutment were completed of concrete works.

Superstructure:

1 span was finished the concrete work.

Girder Production:

5 nos. of 5 girder were finished the production.
 

Bridge No.4

Substructure

All sub-structures were completed for concrete work.

Superstructure

All launching work and deck slabs were completed and remained the expansion joint.

Bridge No.5

Substructure

All sub-structure were completed for concrete work.

Superstructure

All spans were finished the concrete work.

Girder Production

20 nos. of 20 girders is finished production.

Bridge No.6

Substructure

All sub-structures were completed for concrete work.

Superstructure

5 span were finished the launching. All spans were finished the concrete work.

Girder Production

25 nos. of 25 girders were finished the production.

Bridge No.7

Substructure

All sub-structure were completed for concrete work.

Superstructure

4 Spans were finished the launching. All spans were finished the concrete work.

Girder Production

All of girder 20 nos. were finished the production

Road Works

Clearing and grubbing:

All clearing and grubbing area were completed

Earthworks

Excavation work was under construction and 655,860 m3 of 659,000m3 was completed. Embankment work was under construction and 121,218 m3 of 121,218 m3 was completed. Completion percentage of excavation was 99.5% and embankment 100%. Generally, the excavation work was late. The Contractor should speed-up the work progress.

Pavement:

Production of aggregate subbase were at yard. Subbase work were finished in this month as follows:

Subbase course layer 2 were finished at Km8+900 to Km9+397, Km9+580 to Km9+770.

Subbase course layers 1 was finished at Km10+233 to Km10+500 and Km10+633 to Km10+800.

Completed aggregate subbase quantity was about 71.045%

Retainning:

Retaining wall at the back of southern abutment bridge No3 and southern abutment bridge No4 were completed 100%.

Retaining wall at the black of southerm abutment bridge No2 was under construction.

Culvert work:

1. Box culvert at KM9+115 concrete work was completed.

2. Under pass at KM11+260 was completed.

3. Pipe culvert at KM11+050 was completed.

4. Pipe culvert at KM11+290 was completed.

5. Pipe culvert at KM11+660 was not started yet

Schedule overview

Total schedule is just on the schedule based on the new construction schedule establish at November 2003.

Earthwork of road works is also delayed. Contractor was requested to review the equipment schedule.

Earthwork of area 7, area 10 seem to be delayed in comparison with the expected finishing schedule.

Top

Previous month / Next month


This homepage is presented by the Consultant Team

Any further question should be forwarded to Webmaster or Consultant Team

 

 


Progress To Date

By Figure
By Primavera



Tunnel Excavation
Record

By Number
By Figure
By Plan
By Chart




Monthly Progress

Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII



News and Events
Project
Public Media
Visitor List



Organization Charts

The Employer
The Consultant
The Contractors
Others



Consultant Office

List of Staff
Members Only



Project Information
Introduction
(MS-PowerPoint)
Project Map
Background
Major Features
Chronicle
Contract Packages
Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII
Natural Conditions
Socio-Economic Dev.



Public Relations
Site Map
Contact Us
Related Agencies
Link
FAQs
Knowledgebase
Guest Book



Our Gallery
Computer Graphics
Perspective
Vietnam
Introduction
Photo Selection



Around Project
Highway Network in
Vietnam
Large-scaledHighway
Projects in Central
of Vietnam



Tiếng Việt



Coordination