![]() |
|||||||||||||||||||||||||||
Welcome to Our Site! |
|||||||||||||||||||||||||||
Progress Report > Package IIB - Southern HighwaySection
Construction Supervision Summary from Contractor Bridge No.2: All sub-structures were completed for concrete work. All spans of launching and 9 spans of deck slab were completed. Total activities completion was 96%. Progress of construction will be finished at 14th January 2004. Bridge No.3: All sub-structures were completed for concrete work. Launching work was finished. Diaphragm work was finished. Total activities completion was 80%. Progress of construction will be finished at date end of December 2003. Bridge No.4: All sub-structures were completed for concrete work. All launching work and deck slabs were completed and remaining expansion joints. Total activities completion was 98%. Progress of construction will be finished at date end of December 2003. Bridge No.5: All sub-structures were completed for concrete work. All spans of launching and all spans of deck slab were completed. Total activities completion was 97%. Progress of construction will be finished at date end of December 2003. Bridge No.6: All sub-structures were completed for concrete work. All spans of launching and 4 spans of diaphram were completed. 3 spans deck slap were completed. Total activities completion was 82%. Progress of construction will be finished at 30th January 2004. Bridge
No.7: All sub-structures were completed for
concrete work. All launching work and all spans
of deck slap were completed. Total activities completion
was 97%. Progress of construction will be finished
at 23nd January 2004. Construction
Supervision by Engineer Bridge No.2 Substructure
Superstructure
Girder Production
Bridge No.3
Bridge No.4 Substructure
Superstructure
Bridge No.5 Substructure
Superstructure
Girder Production
Bridge No.6 Substructure
Superstructure
Girder Production
Bridge No.7 Substructure
Superstructure
Girder Production
Road Works Clearing and grubbing:
Earthworks
Pavement:
Retainning:
Culvert work:
This homepage is presented by the Consultant Team Any further question should be forwarded to Webmaster or Consultant Team
|
|
||||||||||||||||||||||||||