As of October 31, 2003

Physical Progress

Contractor

JV of Cienco, Lung Lo and Vinawaco

Commencement of the Works

26 July 2001

Contract period

960 days (Until March 25, 2004)

Time Elapsed (days)

815 of 960 (84.89%) Remaining 145 days

Progress

 

Bridge No.2 (334m)

Total completion 95%

Bridge No.3 (033m)

Total completion 70%

Bridge No.4 (175m)

Total completion 98%

Bridge No.5 (133m)

Total completion 90%

Bridge No.6 (150m)

Total completion 74%

Bridge No.7 (133m)

Total completion 84%

Temporary Work

Under construction

Photographs

Top

Construction Supervision

Summary from Contractor

Bridge No.2: All sub-structures were completed for concrete work. 50 nos. of girders were finished the production. 9 spans of launching and 9 spans of deck slab were completed. Total activities completion was 95%. Progress of construction will be finished by the end of December 2003.

Bridge No.3: South Abutment and North Abutment were completed the concrete works. 5 nos. of 5 girder were finished the production. Launching work was completed. Total activities completion was 70%. Progress of construction will be finished by the end of November 2003.

Bridge No.4: All sub-structures were completed for concrete work. All launching work and deck slabs were completed and expansion joints remained. Total activities completion was 98%. Progress of construction will be finished by the end of November 2003.

Bridge No.5: All sub-structures were completed for concrete work. 20 nos. of PCI girders were finished the production. 4 spans of launching and 4 spans of deck slab were completed. Total activities completion was 90%. Progress of construction will be finished by the end of December 2003.

Bridge No.6: All sub-structures were completed for concrete work. 25 nos. of 25 girders were finished the production. 5 spans of launching and 4 spans of diaphram were completed. 1 span deck slap were completed. Total activities completion was 74%. Total progress was 30 days behind from the expected finishing date end of December 2003.

Bridge No.7: All sub-structures were completed for concrete work. 20 nos. of PCI girders were finished the production. All launching work and 3 spans of deck slap were completed. Total activities completion was 84%. Progress of construction will be finished by the end of December 2003.

Construction Supervision by Engineer

Bridge No.2

Substructure

North abutment was completed of concrete works. Pier No.1, 2, 3, 4, 5, 6, 7, 8, 9 were completed of concrete works up to cross head. South abutment was completed of concrete works.

Superstructure

Span 1, 2, 3, 4, 5, 6, 7, 8, 9 were finished the slab concrete and span 9 was finished the launching.

Girder Production

50 nos. of 50 girder was finished production.

Bridge No.3

North Abutment, South Abutment were completed of concrete works. 5 nos. of 5 girder was finished production. 1 span was finished the launching.

Bridge No.4

Substructure

All sub-structures were completed for concrete work.

Superstructure

All sub-structures were completed for concrete work. All launching work and deck slabs were completed and remaining expansion joint.

Bridge No.5

Substructure

All sub-structure were completed for concrete work.

Superstructure

All Spans were finished launching. Diaphram of all spans  were completed. 4 spans of deck slab were completed.

Girder Production

20 nos. of 20 girders is finished production.

Bridge No.6

Substructure

All sub-structures were completed for concrete work.

Superstructure

All spans were finished the launching. Diaphram of spans 1,2,3,4 were completed for concrete work. Span 1 of deck slap was completed.

Girder Production

25 no. of 25 girders were finished the production at girder production yard.

Bridge No.7

Substructure

All sub-structures were completed for concrete work.

Superstructure

All Spans were finished launching. Diaphram of spans 2,3,4 were completed. 3 pans of deck slap were completed for concrete work

Girder Production

All of girder 20 nos. were finished the production

Road Works

Clearing and grubbing:

All clearing and grubbing area were completed

Earthworks

Excavation work was under construction and 630,836 m3 of 659,000m3 was completed. Embankment work was under constructing and 120,819 m3 of 121,218 m3 completed. Percent completion of excavation was 95.7% and embankment 99.7%. Generally, excavation work was late. The Contractor should be speed-up of work progress. Embankment work was being carried out at KM8+125 - KM8+195.

Excavation work was being carried out at KM8+580 to KM8+815, KM11+440 to KM12+00

Pavement:

Production of aggregate subbase was at yard.

Subbase work were finished in this month follows: Subbase course layer 1 was finished at Km8+900 to Km9+397. Subbase course layers 1,2 was finished at Km9+572.25 to Km9+680 and Km9+814.35 to Km10+083.

Completed aggregate subbase quantity was about 45.42%.

Retainning:

Retaining wall at the back of southern abutment bridge No3 and southern abutment bridge No4 was completed 100%. Retaining wall at the black of southerm abutment bridge No2 was carried out foundation excavation.

Culvert work:

1. Box culvert at KM9+115 concrete work was completed.

2. Under pass at KM11+260 was completed.

3. Pipe culvert at KM11+050 was completed.

4. Pipe culvert at KM11+290 was completed.

5. Pipe culvert at KM11+660 was not started yet.

Top

Previous month / Next month


This homepage is presented by the Consultant Team

Any further question should be forwarded to Webmaster or Consultant Team

 

 


Progress To Date

By Figure
By Primavera



Tunnel Excavation
Record

By Number
By Figure
By Plan
By Chart




Monthly Progress

Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII



News and Events
Project
Public Media
Visitor List



Organization Charts

The Employer
The Consultant
The Contractors
Others



Consultant Office

List of Staff
Members Only



Project Information
Introduction
(MS-PowerPoint)
Project Map
Background
Major Features
Chronicle
Contract Packages
Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII
Natural Conditions
Socio-Economic Dev.



Public Relations
Site Map
Contact Us
Related Agencies
Link
FAQs
Knowledgebase
Guest Book



Our Gallery
Computer Graphics
Perspective
Vietnam
Introduction
Photo Selection



Around Project
Highway Network in
Vietnam
Large-scaledHighway
Projects in Central
of Vietnam



Tiếng Việt



Coordination