![]() |
|||||||||||||||||||||||||||
Welcome to Our Site! |
|||||||||||||||||||||||||||
Progress Report > Package IIB - Southern HighwaySection
Construction Supervision Summary from Contractor Bridge No.2: All sub-structures were completed for concrete work. 50 nos. of girders were finished the production. 9 spans of launching and 9 spans of deck slab were completed. Total activities completion was 95%. Progress of construction will be finished by the end of December 2003. Bridge No.3: South Abutment and North Abutment were completed the concrete works. 5 nos. of 5 girder were finished the production. Launching work was completed. Total activities completion was 70%. Progress of construction will be finished by the end of November 2003. Bridge No.4: All sub-structures were completed for concrete work. All launching work and deck slabs were completed and expansion joints remained. Total activities completion was 98%. Progress of construction will be finished by the end of November 2003. Bridge No.5: All sub-structures were completed for concrete work. 20 nos. of PCI girders were finished the production. 4 spans of launching and 4 spans of deck slab were completed. Total activities completion was 90%. Progress of construction will be finished by the end of December 2003. Bridge No.6: All sub-structures were completed for concrete work. 25 nos. of 25 girders were finished the production. 5 spans of launching and 4 spans of diaphram were completed. 1 span deck slap were completed. Total activities completion was 74%. Total progress was 30 days behind from the expected finishing date end of December 2003. Bridge No.7: All sub-structures were completed for concrete work. 20 nos. of PCI girders were finished the production. All launching work and 3 spans of deck slap were completed. Total activities completion was 84%. Progress of construction will be finished by the end of December 2003. Construction
Supervision by Engineer Bridge No.2 Substructure
Superstructure
Girder Production
Bridge No.3
Bridge No.4 Substructure
Superstructure
Bridge No.5 Substructure
Superstructure
Girder Production
Bridge No.6 Substructure
Superstructure
Girder Production
Bridge No.7 Substructure
Superstructure
Girder Production
Road Works Clearing and grubbing:
Earthworks
Pavement:
Retainning:
Culvert work:
This homepage is presented by the Consultant Team Any further question should be forwarded to Webmaster or Consultant Team
|
|
||||||||||||||||||||||||||