As of September 30, 2003

Physical Progress

Contractor

JV of Cienco, Lung Lo and Vinawaco

Commencement of the Works

26 July 2001

Contract period

960 days (Until March 25, 2004)

Time Elapsed (days)

785 of 960 (81.77%) Remaining 175 days

Progress

 

Bridge No.2 (334m)

Total completion 89%

Bridge No.3 (033m)

Total completion 60%

Bridge No.4 (175m)

Total completion 98%

Bridge No.5 (133m)

Total completion 84%

Bridge No.6 (150m)

Total completion 66%

Bridge No.7 (133m)

Total completion 71%

Temporary Work

Under construction

Photographs

Overview of Bridge No.2
Overview of Bridge No.2
Launching Work at Span P8-P9 of Bridge No.2
Launching Work at Bridge No.2
Construction of Abutment A1 of Bridge No.2
Concrete Curing Work of Deck Slab of Bridge No.5
Deck Slab Work of Bridge No.5
Bridge No.6 Under Lauching Girders
Overview of Bridge No.6

Top

Construction Supervision

Bridge No.2

Substructure

North abutment was completed of concrete works. Pier No.1, 2, 3, 4, 5, 6, 7, 8, 9 were completed of concrete works up to cross head. South abutment was under construction of concrete works.

Superstructure

Span 1, 2, 3, 4, 5, 6, 7, 8 were completed the slab concrete and span 9 completed the launching.

Girder Production

49 nos. of girder were produced at casting yard near by north abutment.

Bridge No.3

North Abutment, South Abutment were completed of concrete works. 5 nos. of girders were produced at casting yard near by north abutment.

Bridge No.4

Substructure

All sub-structures were completed for concrete work.

Superstructure

All sub-structures were completed for concrete work. All launching work and deck slabs were completed and remaining expansion joint.

Bridge No.5

Substructure

All sub-structure were completed for concrete work.

Superstructure

All Spans were finished launching. Diaphram of all spans  were completed. Span 2,3,4 were completed slab concrete.

Girder Production

20 nos. of 20 girders is finished production.

Bridge No.6

Substructure

All sub-structures were completed for concrete work.

Superstructure

Span 1, 2, 3, 4 were finished the launching.

Girder Production

25 no. of 25 girders were finished the production at girder production yard.

Bridge No.7

Substructure

All sub-structures were completed for concrete work.

Superstructure

All Spans were finished the launching. Diaphram of  spans 3, 4 were completed. Span 4 have finished slab concrete

Girder Production

All of girder 20 nos. were finished the production

Road Works

Clearing and grubbing:

All clearing and grubbing area were completed

Earthworks

Excavation work was under construction and 620,156 m3 of 659,000m3 was completed. Embankment work  was under construction and 120,521 m3 of 121,218 m3 was completed. Percent completion of excavation was 94.1% and embankment 99.4%. Generally, excavation work was late. The Contractor should speed-up the work progress.

Embankment work was carried out at KM8+125 - KM8+195.

Embankment at, Km9+596 – Km9+678, KM8+860 – KM9+200 were completed.

Production of aggregate subbase and base are being at yard, up to now layer subbase at Km11+00 – Km11+480 and Km0+764.97 – Km1+754.95 (connection road from southern Hai Van tunnel portal to national Highway No1) were completed. Completed aggregate subbase quantity was about 36.9%.

Retainning:

Retaining wall at the back of southern abutment bridge No3 and southern abutment bridge No4 were completed 100%. 

1. Box culvert at KM9+115:

Concrete work for body was completed. 

2. Under pass at KM11+260: Until now concrete work was completed.

3. Pipe culvert at KM11+050: completed.

4. Pipe culvert at KM11+290: completed.

5. Pipe culvert at KM11+660 was not started yet

Top

Previous month / Next month


This homepage is presented by the Consultant Team

Any further question should be forwarded to Webmaster or Consultant Team

 

 


Progress To Date

By Figure
By Primavera



Tunnel Excavation
Record

By Number
By Figure
By Plan
By Chart




Monthly Progress

Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII



News and Events
Project
Public Media
Visitor List



Organization Charts

The Employer
The Consultant
The Contractors
Others



Consultant Office

List of Staff
Members Only



Project Information
Introduction
(MS-PowerPoint)
Project Map
Background
Major Features
Chronicle
Contract Packages
Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII
Natural Conditions
Socio-Economic Dev.



Public Relations
Site Map
Contact Us
Related Agencies
Link
FAQs
Knowledgebase
Guest Book



Our Gallery
Computer Graphics
Perspective
Vietnam
Introduction
Photo Selection



Around Project
Highway Network in
Vietnam
Large-scaledHighway
Projects in Central
of Vietnam



Tiếng Việt



Coordination