![]() |
|||||||||||||||||||||||||||
Welcome to Our Site! |
|||||||||||||||||||||||||||
Progress Report > Package IIB - Southern HighwaySection
Photographs Construction Supervision Summary Bridge No.2: 1 Abutment and 9 piers were completed such as North Abutment, P1, P2, P3, P4, P5, P6, P7, P8, P9. 1 Abutment was under construction such as South Abutment. 48 nos. of girder were finished production at casting yard near by north abutment and remain 2 nos. 8 spans of launching and 8 spans of deck slab were completed. Total activities completion was 86%. Progress of construction will be finished at date end of November 2003. Bridge No.3: South Abutment and North Abutment completed the concrete works. 5 nos. of 5 girder were finished the production at casting yard near by South Abutment. Total activities completion was 60%. Bridge
No.4: All sub-structures were completed for concrete
work. All launching work and deck slabs have been
completed and remaining expansion joints. Total
activities completion was 98%. Bridge
No.5: All sub-structures were completed for concrete
work. 20 nos. of PCI girders were finished the
production and nothing remained. 4 spans of
launching and 2 spans of deck slab were completed.
Total activities completion was 81%. Progress of
construction will be finished at November 20 2003. Bridge No.6: All sub-structures were completed for concrete work. 25 nos. of 25 girders were finished the production. 4 spans of launching were completed. Total activities completion was 58%. Total progress was 30 days behind from the expected finishing date end of December 2003. Bridge No.7: All sub-structures were completed for concrete work. 20 nos. of PCI girders were finished the production and nothing remained. All launching work completed. 2 spans of deck slab were completed. Total activities completion was 68%. Progress of construction will be finished at November 30 2003. Bridge No.2 Substructure
Superstructure
Girder Production
Bridge No.3 North Abutment, South Abutment were completed the concrete works. 5 nos. of girder were produced at casting yard near by north abutment Bridge No.4 Substructure
Superstructure
Bridge No.5 Substructure
Superstructure
Girder Production
Bridge No.6 Substructure
Superstructure
Girder Production
Bridge No.7 Substructure
Superstructure
Girder Production
Road Works Clearing and grubbing:
Earthworks
Pavement:
Retainning:
Culvert work:
This homepage is presented by the Consultant Team Any further question should be forwarded to Webmaster or Consultant Team
|
|
||||||||||||||||||||||||||