Construction
Supervision
Bridge
No.2
Substructure
North
abutment was completed of concrete works.
Pier
No.1, 2, 3, 4, 5, 6, 7, 8, 9 were completed of
concrete works up to cross head.
South
abutment was under construction of concrete works.
Superstructure
Span
1, 2, 3, 4, 5, 6, 7 was completed the slab
concrete and span 7 complete the launching.
Girder
Production
43
nos. of girders were produced at casting yard near
by north abutment.
Bridge
No.3
North
Abutment, South Abutment were completed of
concrete works.
5
nos. of girder were produced at casting yard near
by north abutment.
Bridge
No.4
Substructure
All
sub-structure was completed for concrete work.
Superstructure
All
sub-structures was completed for concrete work.
All
launching work and deck slabs were completed and
remaining expansion joint.
Bridge
No.5
Substructure
All
sub-structure was completed for concrete work.
Superstructure
4
Spans have finished launching.
Diaphram
of span P2-P3 and Span P3-A2 was completed.
Girder
Production
20
nos. of 20 girders is finished production.
Bridge
No.6
Substructure
All
sub-structure was completed for concrete work.
Superstructure
1
Spans completed the launching.
Girder
Production
23
no. of 25 girders was completed the production at
girder production yard.
Bridge
No.7
Substructure
All
sub-structure was completed for concrete work.
Superstructure
4
Spans completed the launching.
Girder
Production
All
of girder 20 nos. completed the production
Road
Works
Earthworks
Excavation
work was under construction and 607,656 m3 of
659,000m3 was completed.
Embankment
work was under construction and 116,169 m3
of 121,218 m3 was completed.
Percent
completion of excavation was 92.2% and embankment
95.8%.