Welcome to Our Site!
 

 

As of July 31, 2003

Physical Progress

Contractor

JV of Cienco, Lung Lo and Vinawaco

Commencement of the Works

26 July 2001

Contract period

960 days (Until March 25, 2004)

Time Elapsed (days)

728 of 960 (75.73%) Remaining 232 days

Progress

 

Bridge No.2 (334m)

Total completion 82%

Bridge No.3 (033m)

Total completion 60%

Bridge No.4 (175m)

Total completion 98%

Bridge No.5 (133m)

Total completion 68%

Bridge No.6 (150m)

Total completion 50%

Bridge No.7 (133m)

Total completion 61%

Temporary Work

Under construction

Photographs

Overview of Bridge No. 2 from Pier 5
The 8th span of Bridge No. 2 under lauching
Bridge No. 3 under lauching the first girder

Backfilling behind abutment A1 of Bridge No. 3

Overview of Bridge No. 5
Lauching work at Bridge No. 6 (the first span)
Bridge No. 7 after finishing lauching girders
Connection road
Road section between Bridge No. 3 and Bridge No. 4
South Toll Plaza

Top

Construction Supervision

Bridge No.2

Substructure

North abutment was completed of concrete works.

Pier No.1, 2, 3, 4, 5, 6, 7, 8, 9 were completed of concrete works up to cross head.

South abutment was under construction of concrete works.

Superstructure

Span 1, 2, 3, 4, 5, 6, 7 was completed the slab concrete and span 7 complete the launching.

Girder Production

43 nos. of girders were produced at casting yard near by north abutment.

Bridge No.3

North Abutment, South Abutment were completed of concrete works.

5 nos. of girder were produced at casting yard near by north abutment.

Bridge No.4

Substructure

All sub-structure was completed for concrete work.

Superstructure

All sub-structures was completed for concrete work.

All launching work and deck slabs were completed and remaining expansion joint.

Bridge No.5

Substructure

All sub-structure was completed for concrete work.

Superstructure

4 Spans have finished launching.

Diaphram of span P2-P3 and Span P3-A2 was completed.

Girder Production

20 nos. of 20 girders is finished production.

Bridge No.6

Substructure

All sub-structure was completed for concrete work.

Superstructure

1 Spans completed the launching.

Girder Production

23 no. of 25 girders was completed the production at girder production yard.

Bridge No.7

Substructure

All sub-structure was completed for concrete work.

Superstructure

4 Spans completed the launching.

Girder Production

All of girder 20 nos. completed the production

Road Works

Earthworks

Excavation work was under construction and 607,656 m3 of 659,000m3 was completed.

Embankment work  was under construction and 116,169 m3 of 121,218 m3 was completed.

Percent completion of excavation was 92.2% and embankment 95.8%.

Top

Previous month / Next month


This homepage is presented by the Consultant Team

Any further question should be forwarded to Webmaster or Consultant Team

 

 


Progress To Date

By Figure
By Primavera



Tunnel Excavation
Record

By Number
By Figure
By Plan
By Chart




Monthly Progress

Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII



News and Events
Project
Public Media
Visitor List



Organization Charts

The Employer
The Consultant
The Contractors
Others



Consultant Office

List of Staff
Members Only



Project Information
Introduction
(MS-PowerPoint)
Project Map
Background
Major Features
Chronicle
Contract Packages
Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII
Natural Conditions
Socio-Economic Dev.



Public Relations
Site Map
Contact Us
Related Agencies
Link
FAQs
Knowledgebase
Guest Book



Our Gallery
Computer Graphics
Perspective
Vietnam
Introduction
Photo Selection



Around Project
Highway Network in
Vietnam
Large-scaledHighway
Projects in Central
of Vietnam



Tiếng Việt



Coordination