Construction
Supervision
Bridge
No.2
Substructure
North
abutment has been completed of concrete works.
Pier
No.1, 2, 3, 4, 5, 6, 7, 8 were completed of
concrete works up to cross head.
Pier
No.9 was under construction of concrete works.
South
abutment under construction of concrete works.
Superstructure
The
slab concrete of span 1, 2, 3,4,5,6 and span 6
completed launching.
Girder
Production
38
nos. of girder have been produced at casting yard
near by north abutment.
Bridge
No.3
North
Abutment, South Abutment have completed of concrete
works.
5
nos. of girder have been produced at casting yard
near by north abutment.
Bridge
No.4
Substructure
All
sub-structure has been completed for concrete
work.
Superstructure
All
sub-structures has completed for concrete work.
All
launching work and deck slabs have been completed
and remaining expansion joint.
Bridge
No.5
Substructure
All
sub-structure has been completed for concrete
work.
Superstructure
4
Spans have finished launching.
Girder
Production
20
nos. of 20 girders is finished production.
Bridge
No.6
Substructure
All
sub-structure has been completed for concrete
work.
Superstructure
Superstructure
is not commenced yet.
Girder
Production
15
no. of 25 girders is finished production at girder
production yard.
Bridge
No.7
Substructure
All
sub-structure has been completed for concrete
work.
Superstructure
4
Spans has finished launching.
Girder
Production
All
of girder 20 nos. have finished production.
Road
Works
Earthworks
Excavation
work is under construction and 576,968 m3 of
659,000m3 has completed.
Embankment
at Km9+115 is under constructing and 103,669 m3 of
121,200m3 has completed.
Percent
completion of excavation is 87.6% and embankment
85.5%.