As of June 30, 2003

Physical Progress

Contractor

JV of Cienco, Lung Lo and Vinawaco

Commencement of the Works

26 July 2001

Contract period

960 days (Until March 25, 2004)

Time Elapsed (days)

698 of 960 (72.7%) Remaining 262 days

Progress

 

Bridge No.2 (334m)

Total completion 74%

Bridge No.3 (33m)

Total completion 60%

Bridge No.4 (175m)

Total completion 97%

Bridge No.5 (133m)

Total completion 61%

Bridge No.6 (150m)

Total completion 50%

Bridge No.7 (133m)

Total completion 61%

Temporary Work

Under construction

Photographs

Abutment A1 of Bridge No. 4 after construction of quarter cone
Lauched spans (P1-A1) of Bridge No. 7
Lauched spans of Bridge No. 7
Blasting work at Km. 11+700
Blasting work at Km. 11+660
Excavation work between Bridge No. 3 and Bridge No. 4
Connection road
Connection road
The first floor of Toll Plaza
Casting the first floor of Toll Plaza

Top

Construction Supervision

Bridge No.2

Substructure

North abutment has been completed of concrete works.

Pier No.1, 2, 3, 4, 5, 6, 7, 8 were completed of concrete works up to cross head.

Pier No.9 was under construction of concrete works.

South abutment under construction of concrete works.

Superstructure

The slab concrete of span 1, 2, 3,4,5,6 and span 6 completed launching.

Girder Production

38 nos. of girder have been produced at casting yard near by north abutment.

Bridge No.3

North Abutment, South Abutment have completed of concrete works.

5 nos. of girder have been produced at casting yard near by north abutment.

Bridge No.4

Substructure

All sub-structure has been completed for concrete work.

Superstructure

All sub-structures has completed for concrete work.

All launching work and deck slabs have been completed and remaining expansion joint.

Bridge No.5

Substructure

All sub-structure has been completed for concrete work.

Superstructure

4 Spans have finished launching.

Girder Production

20 nos. of 20 girders is finished production.

Bridge No.6

Substructure

All sub-structure has been completed for concrete work.

Superstructure

Superstructure is not commenced yet.

Girder Production

15 no. of 25 girders is finished production at girder production yard.

Bridge No.7

Substructure

All sub-structure has been completed for concrete work.

Superstructure

4 Spans has finished launching.

Girder Production

All of girder 20 nos. have finished production.

Road Works

Earthworks

Excavation work is under construction and 576,968 m3 of 659,000m3 has completed.

Embankment at Km9+115 is under constructing and 103,669 m3 of 121,200m3 has completed.

Percent completion of excavation is 87.6% and embankment 85.5%.

Top

Previous month / Next month


This homepage is presented by the Consultant Team

Any further question should be forwarded to Webmaster or Consultant Team

 

 


Progress To Date

By Figure
By Primavera



Tunnel Excavation
Record

By Number
By Figure
By Plan
By Chart




Monthly Progress

Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII



News and Events
Project
Public Media
Visitor List



Organization Charts

The Employer
The Consultant
The Contractors
Others



Consultant Office

List of Staff
Members Only



Project Information
Introduction
(MS-PowerPoint)
Project Map
Background
Major Features
Chronicle
Contract Packages
Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII
Natural Conditions
Socio-Economic Dev.



Public Relations
Site Map
Contact Us
Related Agencies
Link
FAQs
Knowledgebase
Guest Book



Our Gallery
Computer Graphics
Perspective
Vietnam
Introduction
Photo Selection



Around Project
Highway Network in
Vietnam
Large-scaledHighway
Projects in Central
of Vietnam



Tiếng Việt



Coordination