As of May 31, 2003

Physical Progress

Contractor

JV of Cienco, Lung Lo and Vinawaco

Commencement of the Works

26 July 2001

Contract period

960 days (Until March 25, 2004)

Time Elapsed (days)

668 of 960 (69.58%) Remaining 292 days

Progress

 

Bridge No.2 (334m)

Total completion 68%

Bridge No.3 (33m)

Total completion 60%

Bridge No.4 (175m)

Total completion 97%

Bridge No.5 (133m)

Total completion 58%

Bridge No.6 (150m)

Total completion 47%

Bridge No.7 (133m)

Total completion 58%

Temporary Work

Under construction

Photographs

Bridge No.2 Under Launching Girders
Launched Spans (A1-P2) of Bridge No.5
Backfill Work at Abutment A2 of Bridge No.6
Launching Work at Bridge No.7
Bridge No.7 Launching Span P3-P2
Embankment Work from Km.9+115 to Km 9+200
Road Work at Connection Road
Overview of Toll Plaza's Area
Transport Soil From Hoa Nhon Pit to the Site for Top 01m Layer of Embankment
Transportation Work From Hoa Nhon Pit to the Site

Top

Construction Supervision

Bridge No.2

1 Abutment and 8 piers was completed: North Abutment, P1, P2, P3, P4, P5, P6, P7, P8.

1 Abutment and 1 piers was under construction such as South Abutment and P9.

35 nos. of girder were finished production at casting yard near by north abutment and remained 15 nos.

6 spans of launching and 5 spans of deck slab were completed.

Total activities completion is 68%.

Progress of construction will be finished at date end  of November 2003.

Bridge No.3

South Abutment and North Abutment has completed concrete works.

5 nos. of 5 girder are finished production at casting yard near by South Abutment.

Total activities completion is 60%.

Bridge No.4

All sub-structures has completed for concrete work.

All launching work and deck slabs have been completed and remaining expansion joints.

Total activities completion is 97%.

Bridge No.5

All sub-structures has completed for concrete work.

19 nos. of PCI girders are finished production and remain 1nos.

3 span have been launched.

Total activities completion is 58%.

Progress of construction will be finished at November 20 .2003.

Bridge No.6

All sub-structures has completed for concrete work.

8 no. of PCI girders are finished production and remain 17nos.

Total activities completion is 47%.

Total progress is 60 days behind from the expected finishing date end of Dec. 03. 

Bridge No.7

All sub-structures has completed for concrete work.

20 nos. of PCI girders is finished production and remain nothing.

3 span have been launched.

Total activities completion is 58%.

Progress of construction will be finished at November 20 2003.

Top

Previous month / Next month


This homepage is presented by the Consultant Team

Any further question should be forwarded to Webmaster or Consultant Team

 

 


Progress To Date

By Figure
By Primavera



Tunnel Excavation
Record

By Number
By Figure
By Plan
By Chart




Monthly Progress

Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII



News and Events
Project
Public Media
Visitor List



Organization Charts

The Employer
The Consultant
The Contractors
Others



Consultant Office

List of Staff
Members Only



Project Information
Introduction
(MS-PowerPoint)
Project Map
Background
Major Features
Chronicle
Contract Packages
Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII
Natural Conditions
Socio-Economic Dev.



Public Relations
Site Map
Contact Us
Related Agencies
Link
FAQs
Knowledgebase
Guest Book



Our Gallery
Computer Graphics
Perspective
Vietnam
Introduction
Photo Selection



Around Project
Highway Network in
Vietnam
Large-scaledHighway
Projects in Central
of Vietnam



Tiếng Việt



Coordination