Progress Report > Package IIB - Southern HighwaySection
Photographs Construction Supervision Bridge No.2 1 Abutment and 8 piers was completed: North Abutment, P1, P2, P3, P4, P5, P6, P7, P8. 1 Abutment and 1 piers was under construction such as South Abutment and P9. 35 nos. of girder were finished production at casting yard near by north abutment and remained 15 nos. 6 spans of launching and 5 spans of deck slab were completed. Total activities completion is 68%. Progress of construction will be finished at date end of November 2003. Bridge No.3 South Abutment and North Abutment has completed concrete works. 5 nos. of 5 girder are finished production at casting yard near by South Abutment. Total activities completion is 60%. Bridge No.4 All sub-structures has completed for concrete work. All launching work and deck slabs have been completed and remaining expansion joints. Total activities completion is 97%. Bridge No.5 All sub-structures has completed for concrete work. 19
nos. of PCI girders are finished production and
remain 1nos. 3 span have been launched. Total activities completion is 58%. Progress of construction will be finished at November 20 .2003. Bridge No.6 All sub-structures has completed for concrete work. 8 no. of PCI girders are finished production and remain 17nos. Total activities completion is 47%. Total
progress is 60 days behind from the expected
finishing date end of Dec. 03. Bridge No.7 All sub-structures has completed for concrete work. 20 nos. of PCI girders is finished production and remain nothing. 3 span have been launched. Total activities completion is 58%. Progress of construction will be finished at November 20 2003. This homepage is presented by the Consultant Team Any further question should be forwarded to Webmaster or Consultant Team
|
|
||||||||||||||||||||||||||