As of April 30, 2003

Physical Progress

Contractor

JV of Cienco, Lung Lo and Vinawaco

Commencement of the Works

26 July 2001

Contract period

960 days (Until March 25, 2004)

Time Elapsed (days)

638 of 960 (66.46%) Remaining 322 days

Progress

 

Bridge No.2 (334m)

Total completion 59%

Bridge No.3 (33m)

Total completion 60%

Bridge No.4 (175m)

Total completion 97%

Bridge No.5 (133m)

Total completion 52%

Bridge No.6 (150m)

Total completion 47%

Bridge No.7 (133m)

Total completion 52%

Temporary Work

Under construction

Photographs

Abutment A1 of Bridge No.3

Foundation of Retaining Wall of A2 - Bridge No.3

Girder Casting Yard of Bridge No.3

Girder Launching System of Bridge No.5

Span A1 - P1 of Bridge No.5 under Launching

Launching Work at Bridge No.7

Span A2 -P3 of Bridge No.7 under Launching Girder

Girder Launching System of Bridge No.7

Road Section: Backfill Work from Km 9+115 to Km 9+200

Box Culvert at Km 9+115 under Backfill

Blasting Work from Km 11+500 to Km 11+660

Foundation and Reinforcement of Toll Plaza Building

Top

Construction Supervision

Bridge No.2

1 Abutment and 7 piers have been completed such as North Abutment, P1, P2, P3, P4, P5, P6, P7.

1 Abutment and 2 piers are under construction such as South Abutment, P8 and P9

31 nos. of girder are finished production at casting yard near by north abutment and remain 19 nos.

5 spans of launching and 4 spans of deck slab have been completed.

Total activities completion is 59%.

Total progress is 60 days behind from the expected finishing date end of December.2003.

Bridge No.3

South Abutment and North Abutment has completed concrete works.

4 nos. of girder are finished production at casting yard near by South Abutment and remain 1 nos.

Total activities completion is 60%.

Bridge No.4

All sub-structures has completed for concrete work.

All launching work and deck slabs have been completed and remaining expansion joints.

Total activities completion is 97%.

Bridge No.5

All sub-structures has completed for concrete work.

18 nos. of PCI girders are finished production and remain 2nos.

1 span has been launched.

Total activities completion is 52%.

Total progress is 20 days behind from the expected finishing date end of September 2003.

Bridge No.6

All sub-structures has completed for concrete work.

4 no. of PCI girders are finished production and remain 21nos.

Total activities completion is 47%.

Total progress is 66 days behind from the expected finishing date end of October 2003. 

Bridge No.7

All sub-structures has completed for concrete work.

20 nos. of PCI girders is finished production and remain nothing.

1 span have been launched.

Total activities completion is 52%.

Total progress is 15 days behind from the expected finishing date end of Aug.2003.

Top

Previous month / Next month


This homepage is presented by the Consultant Team

Any further question should be forwarded to Webmaster or Consultant Team

 

 


Progress To Date

By Figure
By Primavera



Tunnel Excavation
Record

By Number
By Figure
By Plan
By Chart




Monthly Progress

Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII



News and Events
Project
Public Media
Visitor List



Organization Charts

The Employer
The Consultant
The Contractors
Others



Consultant Office

List of Staff
Members Only



Project Information
Introduction
(MS-PowerPoint)
Project Map
Background
Major Features
Chronicle
Contract Packages
Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII
Natural Conditions
Socio-Economic Dev.



Public Relations
Site Map
Contact Us
Related Agencies
Link
FAQs
Knowledgebase
Guest Book



Our Gallery
Computer Graphics
Perspective
Vietnam
Introduction
Photo Selection



Around Project
Highway Network in
Vietnam
Large-scaledHighway
Projects in Central
of Vietnam



Tiếng Việt



Coordination