Progress Report > Package IIB - Southern HighwaySection
Photographs Construction Supervision Bridge No.2 1 Abutment and 7 piers have been completed such as North Abutment, P1, P2, P3, P4, P5, P6, P7. 1 Abutment and 2 piers are under construction such as South Abutment, P8 and P9 31 nos. of girder are finished production at casting yard near by north abutment and remain 19 nos. 5 spans of launching and 4 spans of deck slab have been completed. Total activities completion is 59%. Total progress is 60 days behind from the expected finishing date end of December.2003. Bridge No.3 South Abutment and North Abutment has completed concrete works. 4 nos. of girder are finished production at casting yard near by South Abutment and remain 1 nos. Total activities completion is 60%. Bridge No.4 All sub-structures has completed for concrete work. All launching work and deck slabs have been completed and remaining expansion joints. Total
activities completion is 97%. Bridge No.5 All sub-structures has completed for concrete work. 18
nos. of PCI girders are finished production and
remain 2nos. 1 span has been launched. Total activities completion is 52%. Total
progress is 20 days behind from the expected
finishing date end of September 2003. Bridge No.6 All sub-structures has completed for concrete work. 4 no. of PCI girders are finished production and remain 21nos. Total activities completion is 47%. Total
progress is 66 days behind from the expected
finishing date end of October 2003. Bridge No.7 All sub-structures has completed for concrete work. 20 nos. of PCI girders is finished production and remain nothing. 1 span have been launched. Total activities completion is 52%. Total progress is 15 days behind from the expected finishing date end of Aug.2003. This homepage is presented by the Consultant Team Any further question should be forwarded to Webmaster or Consultant Team
|
|
||||||||||||||||||||||||||