As of March 31, 2003

Physical Progress

Contractor

JV of Cienco, Lung Lo and Vinawaco

Commencement of the Works

26 July 2001

Contract period 960 days (Until March 25, 2004)
Time Elapsed (days) 608 of 960 (63.30%) Remaining 352 days
Progress
Bridge No.2 (334m) Total completion 53%
Bridge No.3 (33m) Total completion 60%
Bridge No.4 (175m) Total completion 97%
Bridge No.5 (133m) Total completion 48%

Bridge No.6 (150m)

Total completion 47%
Bridge No.7 (133m) Total completion 48%
Temporary Work Under construction

Photographs

Reinforcement of Deck Slab Span P2-P3 of Bridge No.2
Span P3-P4 of Bridge No.2 Under Lauching Girder
Girder Launching System of Bridge No.2
Abutment A1 of Bridge No.3
Girder Casting Yard of Bridge No.3 Under Preparation
Road Work at Km. 9+200
Abutment A2 of Bridge No.7 After Backfill
Roar Work at Toll Plaza Area

Top

Construction Supervision

Bridge No.2

1 Abutment and 6 piers have been completed such as North Abutment, P1, P2, P3, P4, P5, P6.

1 Abutment and 3 piers are under construction such as South Abutment, P7, P8 and P9.

29 nos. of girder are finished production at casting yard near by north abutment and remain 21 nos.

5 spans of launching and 3 spans of deck slab have been completed.

Total activities completion is 53%.

Bridge No.3

South Abutment and North Abutment has completed concrete works.

2 nos. of girder are finished production at casting yard near by South Abutment and remain 3 nos.

Total activities completion is 60%.

Bridge No.4

All sub-structures has completed for concrete work.

All launching work and deck slabs have been completed and remaining expansion joints.

Total activities completion is 97%.

Bridge No.5

All sub-structures has completed for concrete work.

18 nos. of PCI girders are finished production and remain 2nos.

Total activities completion is 48%.

Bridge No.6

All sub-structures has completed for concrete work.

4 no. of PCI girders are finished production and remain 21nos.

Total activities completion is 47%.

Bridge No.7

All sub-structures has completed for concrete work.

20 nos. of PCI girders is finished production and remain nothing.

Total activities completion is 48%.

Top

Previous month / Next month


This homepage is presented by the Consultant Team

Any further question should be forwarded to Webmaster or Consultant Team

 

 


Progress To Date

By Figure
By Primavera



Tunnel Excavation
Record

By Number
By Figure
By Plan
By Chart




Monthly Progress

Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII



News and Events
Project
Public Media
Visitor List



Organization Charts

The Employer
The Consultant
The Contractors
Others



Consultant Office

List of Staff
Members Only



Project Information
Introduction
(MS-PowerPoint)
Project Map
Background
Major Features
Chronicle
Contract Packages
Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII
Natural Conditions
Socio-Economic Dev.



Public Relations
Site Map
Contact Us
Related Agencies
Link
FAQs
Knowledgebase
Guest Book



Our Gallery
Computer Graphics
Perspective
Vietnam
Introduction
Photo Selection



Around Project
Highway Network in
Vietnam
Large-scaledHighway
Projects in Central
of Vietnam



Tiếng Việt



Coordination