Progress Report > Package IIB - Southern HighwaySection
Photographs Construction Supervision Bridge No.2 1 Abutment and 6 piers have been completed such as North Abutment, P1, P2, P3, P4, P5, P6. 1 Abutment and 3 piers are under construction such as South Abutment, P7, P8 and P9. 29 nos. of girder are finished production at casting yard near by north abutment and remain 21 nos. 5 spans of launching and 3 spans of deck slab have been completed. Total activities completion is 53%. Bridge No.3 South Abutment and North Abutment has completed concrete works. 2 nos. of girder are finished production at casting yard near by South Abutment and remain 3 nos. Total activities completion is 60%. Bridge No.4 All sub-structures has completed for concrete work. All launching work and deck slabs have been completed and remaining expansion joints. Total activities completion is 97%. Bridge No.5 All sub-structures has completed for concrete work. 18
nos. of PCI girders are finished production and
remain 2nos. Total activities completion is 48%. Bridge No.6 All sub-structures has completed for concrete work. 4 no. of PCI girders are finished production and remain 21nos. Total activities completion is 47%. Bridge No.7 All sub-structures has completed for concrete work. 20 nos. of PCI girders is finished production and remain nothing. Total activities completion is 48%. This homepage is presented by the Consultant Team Any further question should be forwarded to Webmaster or Consultant Team
|
|
||||||||||||||||||||||||||