Progress Report > Package IIB - Southern HighwaySection
Photographs Construction Supervision Bridge No.2 1 Abutment and 5 piers have been completed such as North Abutment, P1, P2, P3, P4 and P5. 1 Abutment and 4 piers are under construction such as South Abutment, P6, P7, P8 and P9. 24 nos. of girder are finished production at casting yard near by north abutment and remain 26 nos. 3 spans of launching and 2 spans of deck slab have been completed. Total activities completion is 46%. Total progress is 39 days behind from the expected finishing date end of Dec.2003. Bridge No.3 Footing of North Abutment has completed and to continue elevation. South Abutment has completed concrete works. Total activities completion is 50%. Total progress is 20 days behind from the expected finishing date end of Jun.2003. Bridge No.4 All sub-structures has completed for concrete work. All launching work and deck slabs have been completed and remaining expansion joints. Total activities completion is 97%. Bridge No.5 All sub-structures has completed for concrete work. 15
nos. of PCI girders are finished production and
remain 5nos. Total activities completion is 48%. Total progress is 98 days behind from the expected finishing date end of Aug.2003. Bridge No.6 All sub-structures has completed for concrete work. 1 no. of PCI girders are finished production and remain 24nos. Total activities completion is 47%. Total progress is 28 days behind from the expected finishing date end of Oct.2003. Bridge No.7 All sub-structures has completed for concrete work. 20 nos. of PCI girders is finished production and remain nothing. Total activities completion is 48%. Total progress is 76 days behind from the expected finishing date end of Aug.2003. This homepage is presented by the Consultant Team Any further question should be forwarded to Webmaster or Consultant Team
|
|
||||||||||||||||||||||||