Welcome to Our Site!
 

 

As of April 30, 2004

Physical Progress

Contractor

JV of Dong Ah and Song Da

Commencement of the Works

1st October 2000

Contract Period

1460 days (Until September 30, 2004)

Time Elapsed (days)

1290 of 1460 (88.36%) Remaining 170days

Progress

Main Tunnel(2417m)

Excavated 2379m in total (100%)

Evacuation Tunnel(2429m)

Excavated 2411m in total (100%)

Access Road to Water Reservoir.

Completed

Bridge No.1(58m)

Complete concrete placement for handrail 25.00m and concrete at two ends of bridge approach slab.

Others

 

Photographs

South Tunnel Portal
Testing Subbase Layer
Installation of Reinforcement Steel for Side Drain of Evacuation Tunnel
Installation of Formwork for Side Drain of Evacuation Tunnel
Compaction of Base Layer
Construction EMH-6+7
Inspection of Soil Embankment on Cut & Cover Section of South Tunnel Portal
Removal of Temporary Access Ramp for Construction of Cut & Cover Section of STP
Construction of Electric System of SPP
Construction of Electric System of SPP

Top

Construction Supervision

Summary from Contractor

Main Tunnel and Evacuation Tunnel excavation was completely finished.

Bench excavation and tunnel lining were completed.

The rear concrete works is ongoing.

Construction Supervision by Engineer

Main Tunnel Rear Work

Finished

Road work

Embankment of base layer 1: 2423/2423 (m)

Placement of concrete for cable duct finished.

Placement of concrete for construction of centre drain finished

Evacuation Tunnel

Placement side drain: 500/2411.005 (m)

Bridge No. 1

Complete concrete placement for handrail 25.00m and concrete at two ends of bridge approach slab.

Major Events and Issues

Previous month / Next month


This homepage is presented by the Consultant Team

Any further question should be forwarded to Webmaster or Consultant Team

 

 


Progress To Date

By Figure
By Primavera



Tunnel Excavation
Record

By Number
By Figure
By Plan
By Chart




Monthly Progress

Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII



News and Events
Project
Public Media
Visitor List



Organization Charts

The Employer
The Consultant
The Contractors
Others



Consultant Office

List of Staff
Members Only



Project Information
Introduction
(MS-PowerPoint)
Project Map
Background
Major Features
Chronicle
Contract Packages
Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII
Natural Conditions
Socio-Economic Dev.



Public Relations
Site Map
Contact Us
Related Agencies
Link
FAQs
Knowledgebase
Guest Book



Our Gallery
Computer Graphics
Perspective
Vietnam
Introduction
Photo Selection



Around Project
Highway Network in
Vietnam
Large-scaledHighway
Projects in Central
of Vietnam



Tiếng Việt



Coordination