As of March 31, 2004

Physical Progress

Contractor

JV of Dong Ah and Song Da

Commencement of the Works

1st October 2000

Contract Period

1460 days (Until September 30, 2004)

Time Elapsed (days)

1260 of 1460 (86.30%) Remaining 200days

Progress

 

Main Tunnel(2417m)

Excavated 2379m in total (100%)

Evacuation Tunnel(2429m)

Excavated 2411m in total (100%)

Access Road to Water Reservoir.

Completed

Bridge No.1(58m)

Complete concrete placement of bridge surface 25.00m and cast in place concrete parapet of 25m span

Others

 

 

Photographs

South Tunnel Portal
Embankment Sub-base
Sub-base Testing
Paint Test in EP3 - Plaster Motar
Excavation Cable Electric System
Bridge No. 1

Top

Construction Supervision

Summary from Contractor

Main Tunnel and Evacuation Tunnel excavation was completely finished.

Bench excavation and tunnel lining were completed

The rear concrete works is ongoing.

Construction Supervision by Engineer

Cut and Cover Section

Construction of cut and cover section continued.

The items carried out during the month can be quantified as follows:

                      Rock gabions:                                                 285/470 (nos)

                        Structural embankment:                                 2200/7000 (m3)

South Portal

Carrying out construction of electrical system

          Electrical manhole 9+11

          Electrical manhole 8+10

Main Tunnel rear works

Placement of concrete for side drain (East): 32.8m.  Total finish 2423.4m

Road work

Embankment of base layer 1: 2133.0/2423 (m)

Placement of concrete for cable duct: 30.2m.  Total finish 2423.4 m

Placement of concrete for construction of centre drain 229.0m. Total finish 2397.8 m

Main Tunnel rear works

Placement side drain: 50/2411.005 (m)

Bridge No. 1

Complete concrete placement of bridge surface 25.00m and cast in place concrete parapet of 25m span

Major Events and Issues

Previous month / Next month


This homepage is presented by the Consultant Team

Any further question should be forwarded to Webmaster or Consultant Team

 

 


Progress To Date

By Figure
By Primavera



Tunnel Excavation
Record

By Number
By Figure
By Plan
By Chart




Monthly Progress

Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII



News and Events
Project
Public Media
Visitor List



Organization Charts

The Employer
The Consultant
The Contractors
Others



Consultant Office

List of Staff
Members Only



Project Information
Introduction
(MS-PowerPoint)
Project Map
Background
Major Features
Chronicle
Contract Packages
Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII
Natural Conditions
Socio-Economic Dev.



Public Relations
Site Map
Contact Us
Related Agencies
Link
FAQs
Knowledgebase
Guest Book



Our Gallery
Computer Graphics
Perspective
Vietnam
Introduction
Photo Selection



Around Project
Highway Network in
Vietnam
Large-scaledHighway
Projects in Central
of Vietnam



Tiếng Việt



Coordination