Progress Report > Package IB - South Tunnel Section
Main Tunnel and Evacuation Tunnel excavation was completely finished. Bench excavation and tunnel lining were completed. The
rear concrete works is ongoing. Construction Supervision by Engineer Cut
and Cover Section Construction
of cut and cover section continued. Soil
embankment and sodding for slope
1200 m2
South
Portal Electric
system: Already completion of construction for system of
EMH 8+10, EMH 6+7, EMH 9+11, EMH 2, EMH 3, EMH 4, EMH 5,
EMH 12, EMH 13, and some lines of electric cable ducts. Water
system: Construction for OS, OS1, CSC, MH10, MH11, MH12,
Collecting basin, Leach field type A, MH9 are being executed. Main Tunnel Rear Work: Finished
Road
work Embankment
of base layer 2 : 1123 (m) and completed Concrete
pavement East side : 78 (m) Tunnel
lining painting West side : 950 (m) Concrete
placement cover for walk way west side : 400 (m) Evacuation
Tunnel Rear Work Placement
side drain: 670 (m). Total 1170/2435m) Bridge No. 1: Complete concrete placement for handrail 25.00m and concrete at two ends of bridge approach slab. Major Events and Issues This homepage is presented by the Consultant Team Any further question should be forwarded to Webmaster or Consultant Team
|
|
||||||||||||||||||||||||||||||||||||||