As of March 31,2004 

Physical Progress

Contractor

JV of ABB, Kinden and Vinaincon

Commencement of the Works

21 December 2001

Contract period

540 days (Until June 20, 2003)

Time Elapsed (days)

820 of 540 (151.85%) Extended from June 20, 2003

Progress

 

- Complete the remaining works, testing and commissioning mainly protection relay configuration and 110kV cable.

Photographs

110/22kV Substation Operation and Tunnel Control Center Building
110kV Lien Chieu Substation
Testing in 110kV Lien Chieu Substation
Commissioning in 110kV Lien Chieu Substation

Top

Construction Supervision

Major outstanding items of electrical works that were completed in this month included completion of modifications to LV switchboard and diesel generator boards to satisfy contract requirements, replacement of protection relays with upgraded models, testing of 110kV cables, and final testing by ETC of replacement relays and 22kV switchboard. A joint inspection of electrical snag list items is intended in early April.

Work continues in Lien Chieu Substation on VO No. 1 installation works. A major shutdown of the sub-station was carried out starting midnight on 30 March for 24 hours to allow installation of equipment, move main gantry and reconnect overhead system for Hoa Khanh bay as part of V O No. 1. Meetings between PMU85, PTC No. 2, Engineer, and the Contractor continue to be held to coordinate the requirements for the energisation of the Hai Van Pass Tunnel 110kV substation. There is a considerable amount of documentation, presentation of technical information and other paperwork required. It is estimated that Hai Van 110kV substation can be energised in mid April.

The actual energisation and duration (whether 72 hours trial energisation or permanent service) is dependant on EVN concurrence and a final determination of which parties will be responsible for operations and maintenance of what sections of the PKV installed power system. 

It was estimated by the Contractor that all non-electrical items (civil/architectural works) on the snags list would be completed by end of January, 2004 with the remainder in February. A joint inspection was carried out on 1st April of all non-electrical items on snag lists. There are still a small number of outstanding items to be corrected. Relays in the 110kV GIS were replaced with upgraded models by the manufacturer at no cost to the client. Repairs to cracks in the OCC exterior walls were carried out and re-painting completed in February.

The air conditioning and ventilation installation was completed but still has defects in one unit. General furniture (tables, chairs, etc) was delivered to the OCC and most of the remainder including photocopy machines, computers and non-fixed kitchen equipment was in PKV on-site storage for safe keeping.

Top


This homepage is presented by the Consultant Team

Any further question should be forwarded to Webmaster or Consultant Team

 

 


Progress To Date

By Figure
By Primavera



Tunnel Excavation
Record

By Number
By Figure
By Plan
By Chart




Monthly Progress

Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII



News and Events
Project
Public Media
Visitor List



Organization Charts

The Employer
The Consultant
The Contractors
Others



Consultant Office

List of Staff
Members Only



Project Information
Introduction
(MS-PowerPoint)
Project Map
Background
Major Features
Chronicle
Contract Packages
Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII
Natural Conditions
Socio-Economic Dev.



Public Relations
Site Map
Contact Us
Related Agencies
Link
FAQs
Knowledgebase
Guest Book



Our Gallery
Computer Graphics
Perspective
Vietnam
Introduction
Photo Selection



Around Project
Highway Network in
Vietnam
Large-scaledHighway
Projects in Central
of Vietnam



Tiếng Việt



Coordination