As of January 31,2004 

Physical Progress

Contractor

JV of ABB, Kinden and Vinaincon

Commencement of the Works

21 December 2001

Contract period

540 days (Until June 20, 2003)

Time Elapsed (days)

760 of 540 (140%) Extended from June 20, 2003

Progress

 

110/22 kV Substation

- Continue the repairing work for OCC Building.

110 kV Transmission Line

- Test and energise one 110kV feeder (Hai Van feeder).

Photographs

Modification of Crack on Hai Van OCC Building Wall
Concrete Work of Substation Equipment Foundation in Lien Chieu Substation

Top

Construction Supervision

Taking-Over certificate was issued for the main works of PKV contract but excluding Variation Order No. 1 (VO No.1). Included in the certificate was a snag list of outstanding civil/architectural finishing and repair works on the OCC building still to be completed. Also completed was a comprehensive list of electrical items to be completed including documentation, high voltage cable tests and issues that need VO No. 1 completion.

The air conditioning and ventilation installation is still not 100% complete and needs testing upon completion. At month's end the telecom systems had been installed but not tested. Some general furniture (tables, chairs, etc) was delivered to the OCC and most of the remainder including photocopy machines, computers and non-fixed kitchen equipment was in PKV on-site storage for safe keeping.

It was estimated by the Contractor that all non electrical items (civil/architectural works) on the snags list would be completed by end of January, 2004 with the remainder in February. It was also scheduled to test and energise one 110kV feeder (Hai Van feeder) under VO No. 1 in late March and the second (Hoa Khanh) feeder in April. The actual energisation is dependant on EVN concurrence and a determination of which parties will be responsible for operations and maintenance of what sections of the PKV installed power system. Civil Works for VO No. 1 at Lien Chieu substation began on 22 December, 2003 and some foundation works had been completed at month's end.

Top


This homepage is presented by the Consultant Team

Any further question should be forwarded to Webmaster or Consultant Team

 

 


Progress To Date

By Figure
By Primavera



Tunnel Excavation
Record

By Number
By Figure
By Plan
By Chart




Monthly Progress

Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII



News and Events
Project
Public Media
Visitor List



Organization Charts

The Employer
The Consultant
The Contractors
Others



Consultant Office

List of Staff
Members Only



Project Information
Introduction
(MS-PowerPoint)
Project Map
Background
Major Features
Chronicle
Contract Packages
Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII
Natural Conditions
Socio-Economic Dev.



Public Relations
Site Map
Contact Us
Related Agencies
Link
FAQs
Knowledgebase
Guest Book



Our Gallery
Computer Graphics
Perspective
Vietnam
Introduction
Photo Selection



Around Project
Highway Network in
Vietnam
Large-scaledHighway
Projects in Central
of Vietnam



Tiếng Việt



Coordination