Construction Supervision On 12 December a Taking-Over certificate was issued for the main works of PKV contract but excluding Variation Order No. 1 (VO No.1). Included in the certificate was a snag list of outstanding civil/architectural finishing and repair works on the OCC building still to be completed. Also completed was a comprehensive list of electrical items to be completed including documentation, high voltage cable tests and issues that need VO No. 1 completion. The air conditioning and ventilation installation is still not 100% complete and needs testing upon completion. At month's end the telecom and fire alarm and detection systems had been installed. Electronic and general furniture (tables, chairs, etc) was being delivered at months end. It was
estimated by the Contractor that all non electrical items on the snags
list would be completed by end of January, 2004 with the remainder in
February. It was also scheduled to test and energise one 110kV feeder
under VO No. 1 in March and the second feeder in April. The actual energisation
is dependant on EVN concurrence and a determination of which parties
will be responsible for what sections of the PKV installed power system.
Civil Works for VO No. 1 at Lien Chieu substation began on 22 December,
2003. This homepage is presented by the Consultant Team Any further question should be forwarded to Webmaster or Consultant Team
|
|
||||||||||||||||