Physical Progress
Contractor JV of ABB, Kinden and Vinaincon Commencement of the Works 21 December 2001 Contract period 540 days (Until June 20, 2003) Time Elapsed (days) *** Progress 110/22 kV Substation *** 110 kV Transmission Line ***
Contractor
JV of ABB, Kinden and Vinaincon
Commencement of the Works
21 December 2001
Contract period
540 days (Until June 20, 2003)
Time Elapsed (days)
***
Progress
Photographs
Top
Construction Supervision
No data.
Previous month / Next month
This homepage is presented by the Consultant Team
Any further question should be forwarded to Webmaster or Consultant Team
Progress To Date By Figure By Primavera Tunnel Excavation Record By Number By Figure By Plan By Chart Monthly Progress Package IA Package IB Package IIA Package IIB Package III Package IV Package V Package VI Package VII News and Events Project Public Media Visitor List Organization Charts The Employer The Consultant The Contractors Others Consultant Office List of Staff Members Only Project Information Introduction (MS-PowerPoint) Project Map Background Major Features Chronicle Contract Packages Package IA Package IB Package IIA Package IIB Package III Package IV Package V Package VI Package VII Natural Conditions Socio-Economic Dev. Public Relations Site Map Contact Us Related Agencies Link FAQs Knowledgebase Guest Book Our Gallery Computer Graphics Perspective Vietnam Introduction Photo Selection Around Project Highway Network in Vietnam Large-scaledHighway Projects in Central of Vietnam Tiếng Việt Coordination