As of December 31, 2003

Physical Progress

Contractor

JV of Dong Ah and Song Da

Commencement of the Works

1st October 2000

Contract Period

1460 days (Until September 30, 2004)

Time Elapsed (days)

1170 of 1460 (80.13%) Remaining 290days

Progress

Main Tunnel(2417m)

Excavated 2379m in total (100%)

Evacuation Tunnel(2429m)

Excavated 2411m in total (100%)

Access Road to Water Reservoir.

Completed

Bridge No.1(58m)

Concrete work for cross beam & slab reinforcement.

Others

 

Photographs


1B0312OV01.jpg
South Tunnel Portal Area

1B0312ST01.jpg
Inspection for Handing Over Electric Trench for PK 3 & 4

1B0312ST02.jpg
Installation of Formwork for Side Drain on West Side

1B0312ST03.jpg
Installation of Formwork for Side Drain on East Side

1B0312ST04.jpg
Compaction of Foundation for Sidedrain

1B0312ST05.jpg
Placement of Concrete Lining for Main Tunnel

1B0312ST06.jpg
Drilling Face for Bench

1B0312ST07.jpg
Mucking for Bench Excavation

1B0312FA01.jpg
Casting of Catch Basin for Center Drain in Main Tunnel

1B0312FA02.jpg
Installation of Wire Mesh for Cut and Cover Section of E.T

1B0312FA03.jpg
Installation of Geotextile for Cut and Cover of E.T

1B0312B101.jpg
Bridge No.1

Top

Construction Supervision

Summary from Contractor

Main Tunnel and Evacuation Tunnel excavation was completely finished.

Bench excavation was completed to the contract limit at Sta. 2+397.825 then continued for PKIA and finished by 12 December 2003. Total 85.9m excavated on East side and 75.3m excavated on West side.

Tunnel lining continued with 114.5m of main tunnel, 31m of layby completed.

PKIB contractor managed to improve progress of the side drain and cable duct/trough. During December zone M. N & O were completed and handed over to PK4 contractor to commence fire main installation works.

Construction Supervision by Engineer

Main Tunnel

Bench excavation

- 85.9m on East side from Sta. 2+579.5 to 2+655.4 and 75.3m on West side between Sta. 2+587.8 to 2+663.1

Tunnel Lining

Concrete for Tunnel Lining

- 114.5m (10 blocks) from St. 2+283.325 to Sta. 2+397.825 and Layby lining 31m (5 blocks) completed

Backfill grouting for concrete lining from block No. 165 to block No. 167

Quantity cement: 450 kg

Repair of defect concrete lining from block No. 155 to block No. 167

Installation of mole drainpipe 94.5 m

Installation of waterproofing membrane 90 m

Placement of concrete for side drain

461m (East side)

249.9m (West side)

Placement of concrete for cable duct - (East side) 283.9m and cable trough - (West side) 117.1m

Placement of concrete for construction of centre drain 564.2m

Evacuation Tunnel

Excavation completely finished, construction of cut and cover section continued.

Bridge No. 1

Continued with placement of concrete for cross beam and slab reinforcement

Major Events and Issues

Previous month / Next month


This homepage is presented by the Consultant Team

Any further question should be forwarded to Webmaster or Consultant Team

 

 


Progress To Date

By Figure
By Primavera



Tunnel Excavation
Record

By Number
By Figure
By Plan
By Chart




Monthly Progress

Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII



News and Events
Project
Public Media
Visitor List



Organization Charts

The Employer
The Consultant
The Contractors
Others



Consultant Office

List of Staff
Members Only



Project Information
Introduction
(MS-PowerPoint)
Project Map
Background
Major Features
Chronicle
Contract Packages
Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII
Natural Conditions
Socio-Economic Dev.



Public Relations
Site Map
Contact Us
Related Agencies
Link
FAQs
Knowledgebase
Guest Book



Our Gallery
Computer Graphics
Perspective
Vietnam
Introduction
Photo Selection



Around Project
Highway Network in
Vietnam
Large-scaledHighway
Projects in Central
of Vietnam



Tiếng Việt



Coordination