Progress Report > Package IB - South Tunnel Section
Main Tunnel and Evacuation Tunnel excavation was completely finished. Bench excavation was completed to the contract limit at Sta. 2+397.825 then continued for PKIA and finished by 12 December 2003. Total 85.9m excavated on East side and 75.3m excavated on West side. Tunnel lining continued with 114.5m of main tunnel, 31m of layby completed. PKIB contractor managed to improve progress of the side drain and cable duct/trough. During December zone M. N & O were completed and handed over to PK4 contractor to commence fire main installation works. Construction Supervision by Engineer Main Tunnel Bench excavation
Tunnel Lining Concrete for Tunnel Lining
Backfill grouting for concrete lining from block No. 165 to block No. 167 Quantity cement: 450 kg Repair of defect concrete lining from block No. 155 to block No. 167 Installation of mole drainpipe 94.5 m Installation of waterproofing membrane 90 m Placement of concrete for side drain 461m (East side)
Placement of concrete for cable duct - (East side) 283.9m and cable trough - (West side) 117.1m Placement
of concrete for construction of centre drain 564.2m Evacuation Tunnel Excavation completely finished, construction of cut and cover section continued. Bridge No. 1 Continued with placement of concrete for cross beam and slab reinforcement Major Events and Issues This homepage is presented by the Consultant Team Any further question should be forwarded to Webmaster or Consultant Team
|
|
||||||||||||||||||||||