Progress Report > Package IB - South Tunnel Section
Main Tunnel and Evacuation Tunnel excavation was completely finished. Bench excavation and tunnel lining were completed The rear concrete works is ongoing. Construction Supervision by Engineer Main Tunnel Tunnel Lining Backfill grouting for concrete lining from block Layby No. 36 to block No. 38 Placement of concrete for side drain 152.7 m (East side)
Placement of concrete for cable duct
Placement of concrete for construction of centre drain 237.8m Evacuation Tunnel Excavation completely finished, construction of cut and cover section continued. The items carried out during the month can be quantified as follows: Geotextile: 320 m2 Waterproofing membrane: 320 m2 CQS6: 320 m2 Shotcrete protection 100mm: 320 m2 Bridge No. 1 Continued with placement of concrete for cross beam and slab reinforcement. Major Events and Issues This homepage is presented by the Consultant Team Any further question should be forwarded to Webmaster or Consultant Team
|
|
||||||||||||||||||||||