Welcome to Our Site!
 

 

Progress Report > Package III - Electrical Works

As of November 30, 2002

Physical Progress

Contractor

JV of ABB, Kinden and Vinaincon

Commencement of the Works

14 February 2003

Contract Period 26 months (Until April 13, 2005)
Time Elapsed (days) 287 of 780 (36.79%) Remaining 493days

Progress

 

- Continue the electrical conduit installation work and submit manufacturer's capability/certification materials and technical data for approval.

 

Photographs

Top

Construction Supervision

The Contractor continued with electrical works installations in North and South Toll Plaza buildings but at a very slow pace. These are the only site works under this contract at this time while waiting to install the earthing grid in EP2 and the adit connection substation. The majority of work at site is the preparation and submittal of manufacturer's materials and installation shop drawings.

PKIII has participated in the hand over of sections of walkways in the tunnel from the civil contractors. The hand over allows PKIII (and PKIV) access to install conduit in the trench under the walkways.

Coordination is ongoing between PKIII and PKIV for space, ventilation and cableway requirements at substations in the Electrostatic Precipitator areas (S/S 1, 2 and 4) and at the Ventilation Adit Building (S/S 6), S/S 3 at adit fresh air discharge near tunnel. Generally most significant issues have been resolved between PKIII and PKIV in those areas. However the size of UPS battery rooms is still to be confirmed following Contractor identification of the fact that he had sized batteries to 30 minutes duration instead of Addendum No. 1 requirements. This issue should be resolved in early December. The final shape and size of S/S # 5 was agreed and design modification of PK1A building contract drawings carried out in-house.

The Contractor continued to submit manufacturer's capability/certification materials and technical data for approval as suppliers of major systems and subsystems.

Top

Previous month / Next month


This homepage is presented by the Consultant Team

Any further question should be forwarded to Webmaster or Consultant Team

 

 


Progress To Date

By Figure
By Primavera



Tunnel Excavation
Record

By Number
By Figure
By Plan
By Chart




Monthly Progress

Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII



News and Events
Project
Public Media
Visitor List



Organization Charts

The Employer
The Consultant
The Contractors
Others



Consultant Office

List of Staff
Members Only



Project Information
Introduction
(MS-PowerPoint)
Project Map
Background
Major Features
Chronicle
Contract Packages
Package IA
Package IB
Package IIA
Package IIB
Package III
Package IV
Package V
Package VI
Package VII
Natural Conditions
Socio-Economic Dev.



Public Relations
Site Map
Contact Us
Related Agencies
Link
FAQs
Knowledgebase
Guest Book



Our Gallery
Computer Graphics
Perspective
Vietnam
Introduction
Photo Selection



Around Project
Highway Network in
Vietnam
Large-scaledHighway
Projects in Central
of Vietnam



Tiếng Việt



Coordination