Progress Report > Package III - Electrical Works
The Contractor continued with electrical works installations in North and South Toll Plaza buildings but at a very slow pace. At the end of September Contractor began installation work of earthing mesh in EP1 for substation No. 4. These are the only site works under this contract at this time. The majority of work at site is the preparation and submittal of manufacturers for approval and some shop drawings. Coordination is ongoing between PKIII and PKIV for space, ventilation and cableway requirements at substations in the Electrostatic Precipitator areas (S/S 1, 2 and 4) and at the Ventilation Adit Building (S/S 6), S/S 3 at adit fresh air discharge near tunnel. Generally all significant issues have been resolved between PKIII and PKIV in those areas. The final shape and size of S/S # 5 was agreed and design modification of PK1A building contract drawings carried out in-house. The Contractor continued to submit manufacturer's capability/certification materials and technical data for approval as suppliers of major systems and subsystems. Electrical power systems engineer arrived on site from ABB Finland to support submittals work, shop drawing development, and help coordinate issues with PKIV. He is also working on PKV commissioning. This homepage is presented by the Consultant Team Any further question should be forwarded to Webmaster or Consultant Team
|
|
||||||||||||||